A and B can do a work in 15 days and 25 ...

A and B can do a work in 15 days and 25 days, respectively. They worked together for 5 days, after which B was replaced by C and the remaining work was completed by A and C in the next 4 days. In how many days will C alone complete the same work ?

A

24 days

B

20 days

C

15 days

D

25 days

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Similar Questions

Explore conceptually related problems

A and B can separately do a piece of work in 20 and 15 days respectively. They worked together for 6 days, after which B was replaced by C. If work was finished in next 4 days, then the number of days in which C alone could do the work will be a. 30 b. 40 c. 35 d. 60

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in:

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?