Home
Class 14
MATHS
A,B and C can do a piece of work in 10,1...

A,B and C can do a piece of work in 10,15 and 30 days, respectively. If B and C both assist A on every third day, then in how many days can the work be completed?

A

`8 1/2`

B

`5`

C

`8`

D

`7 1/2`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much work A, B, and C can complete together, given their individual work rates, and how the work progresses over the days according to the conditions provided. ### Step 1: Determine the work rates of A, B, and C. - A can complete the work in 10 days, so A's work rate is \( \frac{1}{10} \) of the work per day. - B can complete the work in 15 days, so B's work rate is \( \frac{1}{15} \) of the work per day. - C can complete the work in 30 days, so C's work rate is \( \frac{1}{30} \) of the work per day. ### Step 2: Calculate the combined work rate of A, B, and C. On the days when B and C assist A (every third day), we need to calculate their combined work rate: - Combined work rate of A, B, and C on the third day: \[ \text{Work rate} = \frac{1}{10} + \frac{1}{15} + \frac{1}{30} \] To add these fractions, we need a common denominator. The least common multiple of 10, 15, and 30 is 30. \[ \frac{1}{10} = \frac{3}{30}, \quad \frac{1}{15} = \frac{2}{30}, \quad \frac{1}{30} = \frac{1}{30} \] So, \[ \text{Combined work rate} = \frac{3}{30} + \frac{2}{30} + \frac{1}{30} = \frac{6}{30} = \frac{1}{5} \] ### Step 3: Calculate the work done in a 3-day cycle. - On the first two days, only A works: \[ \text{Work done by A in 2 days} = 2 \times \frac{1}{10} = \frac{2}{10} = \frac{1}{5} \] - On the third day, A, B, and C work together: \[ \text{Work done on the third day} = \frac{1}{5} \] - Total work done in 3 days: \[ \text{Total work in 3 days} = \frac{1}{5} + \frac{1}{5} = \frac{2}{5} \] ### Step 4: Determine how many cycles are needed to complete the work. To complete the entire work (1 unit of work), we need to find out how many 3-day cycles are required: - In each cycle of 3 days, \( \frac{2}{5} \) of the work is completed. - Let \( n \) be the number of cycles needed: \[ n \times \frac{2}{5} = 1 \implies n = \frac{5}{2} = 2.5 \] This means we need 2 complete cycles (6 days) and a part of another cycle. ### Step 5: Calculate the remaining work after 2 cycles. - Work done in 2 cycles (6 days): \[ 2 \times \frac{2}{5} = \frac{4}{5} \] - Remaining work: \[ 1 - \frac{4}{5} = \frac{1}{5} \] ### Step 6: Calculate how much time is needed to complete the remaining work. - On the 7th day, A works alone: \[ \text{Work done by A on 7th day} = \frac{1}{10} \] - On the 8th day, A works alone again: \[ \text{Work done by A on 8th day} = \frac{1}{10} \] - On the 9th day, A, B, and C work together: \[ \text{Work done on 9th day} = \frac{1}{5} \] After the 8th day, A has done \( \frac{1}{5} \) of the work, and on the 9th day, they complete the remaining \( \frac{1}{5} \) of the work. ### Total Days Taken - Total days = 6 days (2 cycles) + 2 days (7th and 8th) + 1 day (9th) = 9 days. Thus, the total time taken to complete the work is **9 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?

A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?