Home
Class 14
MATHS
Two workers A and B are engaged to do a...

Two workers A and B are engaged to do a piece of work . A working alone would take 14 hours more to complete the work than when A and B work together B working alone would take ` 3 (1)/(2)` hours more than when A and B work together . The time required to finish the work together is

A

7 hours

B

5 hours

C

6 hours

D

8 hours

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, let's denote the time taken by A and B to complete the work together as \( x \) hours. 1. **Express the time taken by A and B:** - If A works alone, he takes \( x + 14 \) hours. - If B works alone, he takes \( x + 3.5 \) hours. 2. **Set up the work equations:** - The work done by A in one hour is \( \frac{1}{x + 14} \). - The work done by B in one hour is \( \frac{1}{x + 3.5} \). - The work done by A and B together in one hour is \( \frac{1}{x} \). 3. **Combine the work equations:** \[ \frac{1}{x + 14} + \frac{1}{x + 3.5} = \frac{1}{x} \] 4. **Clear the fractions by multiplying through by \( x(x + 14)(x + 3.5) \):** \[ x(x + 3.5) + x(x + 14) = (x + 14)(x + 3.5) \] 5. **Expand and simplify:** - Left side: \( x^2 + 3.5x + x^2 + 14x = 2x^2 + 17.5x \) - Right side: \( x^2 + 3.5x + 14x + 49 = x^2 + 17.5x + 49 \) So we have: \[ 2x^2 + 17.5x = x^2 + 17.5x + 49 \] 6. **Rearranging the equation:** \[ 2x^2 - x^2 + 17.5x - 17.5x - 49 = 0 \] \[ x^2 - 49 = 0 \] 7. **Solve for \( x \):** \[ x^2 = 49 \implies x = 7 \text{ (since time cannot be negative)} \] Thus, the time required to finish the work together is **7 hours**.
Promotional Banner

Similar Questions

Explore conceptually related problems

Two workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 4(1)/(2) hours more to complete the work than if both worked together. How much time would they take to complete the job working together?

Two workers A and B are engaged to do a piece of work.Working alone, A takes 8 hours more to complete the workthan if both worked together. On the other hand, workingalone, B would need 4 1/2 hours more to complete the work than if both worked together. How much time would they take tocomplete the job working together?

A takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?

When A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?

When A alone does a piece of work , he takes 25 days more than the time taken (A+B) to completes that particular work, while B alone takes 49 days more than the time taken by (A + B) to finish the same work. A andBtogether will take what time to finish this work?