Home
Class 14
MATHS
X and Y together can do a piece of work ...

X and Y together can do a piece of work in 10 days .X is 40 % more efficient than Y.X alone will completes 35 % of the same work in :

A

6 days

B

8 days

C

9 days

D

5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we can follow the below approach: ### Step 1: Determine the efficiency of X and Y Given that X is 40% more efficient than Y, we can express their efficiencies in terms of Y's efficiency. Let the efficiency of Y be \( E_Y \). Then, the efficiency of X, \( E_X \), can be expressed as: \[ E_X = E_Y + 0.4 \cdot E_Y = 1.4 \cdot E_Y \] ### Step 2: Calculate the combined efficiency of X and Y When X and Y work together, their combined efficiency is: \[ E_{X+Y} = E_X + E_Y = 1.4E_Y + E_Y = 2.4E_Y \] ### Step 3: Calculate the total work done by X and Y together in 10 days We know that X and Y together can complete the work in 10 days. Therefore, the total work \( W \) can be calculated as: \[ W = E_{X+Y} \times \text{Time} = 2.4E_Y \times 10 = 24E_Y \] ### Step 4: Calculate the work done by X alone Now, we need to find out how much work X can complete alone. We know that X will complete 35% of the total work \( W \): \[ \text{Work done by X} = 0.35W = 0.35 \times 24E_Y = 8.4E_Y \] ### Step 5: Calculate the time taken by X to complete 35% of the work To find the time \( T \) taken by X to complete this work, we can use the formula: \[ T = \frac{\text{Work}}{\text{Efficiency}} = \frac{8.4E_Y}{1.4E_Y} \] The \( E_Y \) cancels out: \[ T = \frac{8.4}{1.4} = 6 \text{ days} \] ### Final Answer Thus, X alone will complete 35% of the same work in **6 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 15 days. B is 50% more efficient than A, B can finish it in

A can do a piece of work in 6 days. B is 25% more efficient than A. How long would B alone take to finish this work?

X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is :

A can complete a piece of work in 12 days. B is 60% more efficient than A. The number of days, that B will take to complete the same work, is

P can do a piece of work in 9 days.Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :