(A + B) can do a piece of work in 20 days and A can do same work in 60 days. In how many days will B do this work ?

A

50

B

75

C

30

D

40

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 16 days and B can do the same work in 20 days.In how many days can they do the same work,working together?

A can do (1)/(10) th of a piece of work in a day. B can do the same work in 15 days. In how many days can they do the same work, working together?

A can do a work in 20 days and B can do the same work in 30 days. In how many days, can A and B together do the work? (A) 10 (B) 12 (C) 15 (D) 16

A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?