Home
Class 14
MATHS
'A' can complete the 60% of the work in ...

'A' can complete the 60% of the work in 9 days, while 'B' can complete the work in `7 1/2` days. If they work together, then in how many days will the work be completed?

A

7

B

6

C

5

D

0.04

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how much work 'A' and 'B' can complete together in a day and then find out how many days it will take them to finish the entire work. ### Step-by-Step Solution: 1. **Calculate the total work done by 'A':** - 'A' completes 60% of the work in 9 days. - Therefore, the total work (let's denote it as W) can be calculated as: \[ 0.6W = \text{Work done by A in 9 days} \] \[ W = \frac{0.6W}{0.6} = \frac{9}{0.6} = 15 \text{ days (for 100% work)} \] 2. **Calculate the work rate of 'A':** - If 'A' completes the entire work in 15 days, then the work rate of 'A' is: \[ \text{Rate of A} = \frac{1}{15} \text{ (work per day)} \] 3. **Calculate the work rate of 'B':** - 'B' can complete the work in \(7 \frac{1}{2}\) days, which is equal to \(7.5\) days. - Therefore, the work rate of 'B' is: \[ \text{Rate of B} = \frac{1}{7.5} = \frac{2}{15} \text{ (work per day)} \] 4. **Calculate the combined work rate of 'A' and 'B':** - When 'A' and 'B' work together, their combined work rate is: \[ \text{Combined Rate} = \text{Rate of A} + \text{Rate of B} = \frac{1}{15} + \frac{2}{15} = \frac{3}{15} = \frac{1}{5} \text{ (work per day)} \] 5. **Calculate the total time taken to complete the work together:** - If they complete \(\frac{1}{5}\) of the work in one day, then the total time taken to complete the entire work (1 unit of work) is: \[ \text{Time} = \frac{1 \text{ (total work)}}{\frac{1}{5} \text{ (work per day)}} = 5 \text{ days} \] ### Final Answer: Thus, 'A' and 'B' together will complete the work in **5 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

The ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?