Home
Class 14
MATHS
X and Y can complete a certain work in 1...

X and Y can complete a certain work in 16 days and 24 days , respectively. The work together for 4 days. Z alone completes the remaining work in `10(1)/(2)` days. Y and Z together can complete `(7)/(8)`th part of the same work in :

A

10 days

B

8 days

C

9 days

D

12 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of X, Y, and Z, and then find out how long Y and Z will take to complete \( \frac{7}{8} \) of the work together. ### Step 1: Determine the work rates of X and Y - X can complete the work in 16 days, so the work done by X in one day is: \[ \text{Work rate of X} = \frac{1}{16} \text{ (work/day)} \] - Y can complete the work in 24 days, so the work done by Y in one day is: \[ \text{Work rate of Y} = \frac{1}{24} \text{ (work/day)} \] ### Step 2: Calculate the combined work rate of X and Y - The combined work rate of X and Y when they work together is: \[ \text{Combined work rate} = \frac{1}{16} + \frac{1}{24} \] - To add these fractions, we find a common denominator, which is 48: \[ \frac{1}{16} = \frac{3}{48}, \quad \frac{1}{24} = \frac{2}{48} \] - Therefore, \[ \text{Combined work rate} = \frac{3}{48} + \frac{2}{48} = \frac{5}{48} \text{ (work/day)} \] ### Step 3: Calculate the work done by X and Y in 4 days - In 4 days, the amount of work done by X and Y together is: \[ \text{Work done in 4 days} = 4 \times \frac{5}{48} = \frac{20}{48} = \frac{5}{12} \] ### Step 4: Determine the remaining work - The total work is considered as 1 unit. Therefore, the remaining work after X and Y have worked for 4 days is: \[ \text{Remaining work} = 1 - \frac{5}{12} = \frac{7}{12} \] ### Step 5: Determine Z's work rate - Z completes the remaining work in \( 10 \frac{1}{2} \) days, which is \( \frac{21}{2} \) days. Thus, Z's work rate is: \[ \text{Work rate of Z} = \frac{1}{\frac{21}{2}} = \frac{2}{21} \text{ (work/day)} \] ### Step 6: Calculate the work rate of Y and Z together - The combined work rate of Y and Z is: \[ \text{Work rate of Y and Z} = \frac{1}{24} + \frac{2}{21} \] - To add these fractions, we find a common denominator, which is 168: \[ \frac{1}{24} = \frac{7}{168}, \quad \frac{2}{21} = \frac{16}{168} \] - Therefore, \[ \text{Combined work rate of Y and Z} = \frac{7}{168} + \frac{16}{168} = \frac{23}{168} \text{ (work/day)} \] ### Step 7: Calculate the time taken by Y and Z to complete \( \frac{7}{8} \) of the work - To find out how long it takes Y and Z to complete \( \frac{7}{8} \) of the work, we set up the equation: \[ \text{Time} = \frac{\text{Work}}{\text{Work rate}} = \frac{\frac{7}{8}}{\frac{23}{168}} = \frac{7}{8} \times \frac{168}{23} \] - Simplifying this gives: \[ = \frac{7 \times 21}{23} = \frac{147}{23} \text{ days} \] ### Conclusion Thus, Y and Z together can complete \( \frac{7}{8} \) of the work in \( \frac{147}{23} \) days.
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in:

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days, B had to leave and A alone completed the remaining work. The whole work was completed in: