A is 30% more efficient than B. If B finishes a work in 13 days, then in how many days will A finish the same work?

A

11

B

9

C

10

D

12

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the efficiency of A and B, and then calculate how many days A will take to finish the work. ### Step 1: Understand the efficiency relationship A is 30% more efficient than B. This means if B's efficiency is considered as 100%, then A's efficiency will be: \[ \text{Efficiency of A} = 100\% + 30\% = 130\% \] ### Step 2: Convert efficiencies to a ratio We can express the efficiencies in a ratio: - Efficiency of B = 100 (let's assume B's efficiency is 100 units of work per day) - Efficiency of A = 130 (A's efficiency is 130 units of work per day) ### Step 3: Determine the work done by B If B finishes the work in 13 days, we can calculate the total work done: \[ \text{Total Work} = \text{Efficiency of B} \times \text{Time taken by B} = 100 \times 13 = 1300 \text{ units of work} \] ### Step 4: Calculate the time taken by A Now, we can find out how many days A will take to finish the same work. Since A's efficiency is 130 units of work per day, we can use the formula: \[ \text{Time taken by A} = \frac{\text{Total Work}}{\text{Efficiency of A}} = \frac{1300}{130} = 10 \text{ days} \] ### Final Answer A will finish the work in **10 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

A is 40 % more efficient than B. If B can complete this work in 24 days. In how many days will both A and B complete this work ?

A works twice as fast as B and B works twice as fast as C. All three working together can finish a task in 4 days with the help of D. If D alone can finish the same task in 16 days, then in how many days will A alone finish 75% of the same task ?