Home
Class 14
MATHS
A can do a piece of work in 12 days and ...

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

A

10 days

B

9 days

C

12 days

D

15 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to find out how many days C can complete the work alone after A and B have worked together for 5 days. ### Step 1: Calculate the work done by A and B in one day. - A can complete the work in 12 days, so A's work rate is \( \frac{1}{12} \) of the work per day. - B can complete the work in 20 days, so B's work rate is \( \frac{1}{20} \) of the work per day. **Hint:** To find the work done in one day, use the formula: Work rate = Total work / Time taken. ### Step 2: Find the combined work rate of A and B. To find the combined work rate of A and B, we add their individual work rates: \[ \text{Combined work rate} = \frac{1}{12} + \frac{1}{20} \] To add these fractions, we need a common denominator. The least common multiple of 12 and 20 is 60. \[ \frac{1}{12} = \frac{5}{60}, \quad \frac{1}{20} = \frac{3}{60} \] So, \[ \text{Combined work rate} = \frac{5}{60} + \frac{3}{60} = \frac{8}{60} = \frac{2}{15} \] **Hint:** When adding fractions, find a common denominator to make the addition easier. ### Step 3: Calculate the total work done by A and B in 5 days. Now, we can find out how much work A and B can complete together in 5 days: \[ \text{Work done in 5 days} = 5 \times \frac{2}{15} = \frac{10}{15} = \frac{2}{3} \] **Hint:** To find the total work done over multiple days, multiply the daily work rate by the number of days. ### Step 4: Determine the remaining work. Since A and B completed \( \frac{2}{3} \) of the work, the remaining work is: \[ \text{Remaining work} = 1 - \frac{2}{3} = \frac{1}{3} \] **Hint:** To find the remaining work, subtract the completed work from the total work (which is considered as 1). ### Step 5: Calculate C's work rate. C completes the remaining work in 3 days, so C's work rate is: \[ \text{C's work rate} = \frac{1}{3} \text{ (work)} \div 3 \text{ (days)} = \frac{1}{9} \] **Hint:** To find the work rate, divide the amount of work by the time taken. ### Step 6: Find out how many days C can do the work alone. To find out how many days C can complete the entire work alone, we take the reciprocal of C's work rate: \[ \text{Days taken by C} = \frac{1}{\frac{1}{9}} = 9 \text{ days} \] **Hint:** To find the time taken to complete the work, take the reciprocal of the work rate. ### Final Answer: C can complete the same work alone in **9 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A can complete one-third of a work in 10 days and B can do ""_(5)^(3) th of the same work in 24 days. They worked together for 10 days. The remaining work was completed by C alone in 15 days. In how many days can C alone do ""_(3)^(2) of the same work?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

A and B can finish a work together in 12 days, and B and C together in 16 days. If A alone works for 5 days and then B alone continues for 7 days, then remaining work is done by C in 13 days. In how many days can C alone finish the complete work?

A can do a piece of work in 120 days and B can do it in 150 days.The work together for 20 days.Then,B leave and A alone continues the work.12 days after that C joins A and the work.is completed in 48 days more.In how many days can C do it,if he works alone?