Last year, 5 companies had an average of...

Last year, 5 companies had an average of 16 non working days each. This year, 3 companies had 10 more non working days each, and 2 companies had 5 fewer non working days each. What was the average number of non working days given by the same companies this year?

A

12

B

18

C

20

D

22

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Similar Questions

Explore conceptually related problems

Kareena can do a piece of work in 9 days and Karishma can do the same work in 18 days. They started the work. After 3 days Shahid joined them, who can complete alone the same whole work in 3 days. What is the total number of days in which they had completed the work?

The Bar graph given below presents the number of males and females working in five different companies. What is the average number of females working per company ?

If 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is

A can do a piece of work in 7 days of 9 hours each and B can do it in 6 days of 7 hours each. How long will they take to do it,working a together 8(2)/(5) a day?

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

If 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, the number of days required to complete the work by 5 men and 6 women is