Home
Class 14
MATHS
A can do a piece of work in 12 days and ...

A can do a piece of work in 12 days and B in 24 days. If they work togeher, in how many days will they finish the work?

A

15 days

B

20 days

C

12days

D

8 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem of how many days A and B will take to finish the work together, we can follow these steps: ### Step 1: Determine the work done by A and B individually. - A can complete the work in 12 days. Therefore, A's work rate (efficiency) is: \[ \text{Efficiency of A} = \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \text{ work per day} \] - B can complete the work in 24 days. Therefore, B's work rate (efficiency) is: \[ \text{Efficiency of B} = \frac{1 \text{ work}}{24 \text{ days}} = \frac{1}{24} \text{ work per day} \] ### Step 2: Calculate the combined work rate of A and B. - To find their combined efficiency, we add the individual efficiencies: \[ \text{Combined Efficiency} = \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{12} + \frac{1}{24} \] - To add these fractions, we need a common denominator. The least common multiple of 12 and 24 is 24. Thus: \[ \frac{1}{12} = \frac{2}{24} \] \[ \text{Combined Efficiency} = \frac{2}{24} + \frac{1}{24} = \frac{3}{24} = \frac{1}{8} \text{ work per day} \] ### Step 3: Calculate the total time taken to complete the work together. - Since their combined efficiency is \(\frac{1}{8}\) work per day, it means together they can complete the work in: \[ \text{Time taken} = \frac{1 \text{ work}}{\text{Combined Efficiency}} = \frac{1}{\frac{1}{8}} = 8 \text{ days} \] ### Final Answer: A and B will finish the work together in **8 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?

A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?

A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?

A can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?

A and B can do piece of work in 12 days; B and C in 15days;C and A in 20 days.In how many days will they finish it together and separately ?

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?