Home
Class 14
MATHS
A and B working together can complete 45...

A and B working together can complete 45% of a work in 18 days. A alone can complete the same work in 60 days. A and B work together for 16 days, and then A leaves. B alone will complete the remaining work in

A

80 days

B

60 days

C

72 days

D

75 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A and B, and then find out how long B will take to complete the remaining work after A leaves. ### Step 1: Determine the work rate of A and B together A and B together can complete 45% of the work in 18 days. To find their combined work rate: - Work completed in 18 days = 45% of the work - Therefore, in 1 day, A and B together complete: \[ \text{Work rate of A and B} = \frac{45\%}{18} = \frac{0.45}{18} = 0.025 \text{ (work per day)} \] ### Step 2: Determine the work rate of A alone A can complete the entire work in 60 days. Thus, A's work rate is: \[ \text{Work rate of A} = \frac{100\%}{60} = \frac{1}{60} \text{ (work per day)} \] ### Step 3: Determine the work rate of B Let the work rate of B be \( b \). From the combined work rate of A and B: \[ \text{Work rate of A} + \text{Work rate of B} = \text{Work rate of A and B} \] \[ \frac{1}{60} + b = 0.025 \] To find \( b \): \[ b = 0.025 - \frac{1}{60} \] Convert \( \frac{1}{60} \) to a decimal: \[ \frac{1}{60} \approx 0.01667 \] So, \[ b = 0.025 - 0.01667 = 0.00833 \text{ (work per day)} \] ### Step 4: Calculate the total work Since A and B together can complete 100% of the work in: \[ \text{Total work} = \frac{1}{\text{Work rate of A and B}} = \frac{1}{0.025} = 40 \text{ days} \] ### Step 5: Calculate the work done by A and B in 16 days In 16 days, A and B together will complete: \[ \text{Work done in 16 days} = 16 \times 0.025 = 0.4 \text{ (or 40% of the work)} \] ### Step 6: Calculate the remaining work The remaining work after 16 days is: \[ \text{Remaining work} = 100\% - 40\% = 60\% \] ### Step 7: Calculate how long B will take to complete the remaining work B's work rate is \( 0.00833 \) (work per day). To find the time \( t \) taken by B to complete the remaining 60% of the work: \[ t = \frac{\text{Remaining work}}{\text{Work rate of B}} = \frac{0.6}{0.00833} \approx 72 \text{ days} \] ### Final Answer B alone will complete the remaining work in approximately **72 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can complete 33(1)/(3) % of a work in 5 days and B can complete 40% of the same work in 10 days. They work together for 5 days and then B left the work. A alone will complete the remaining work in:

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?