Home
Class 14
MATHS
A can do (7)/(8) of work in 28 days, B c...

A can do `(7)/(8)` of work in 28 days, B can do `(5)/(6)` of the same work in 20 days. The number of days they will take to complete if they do it together is .

A

`15(3)/(7)` days

B

`17(3)/(5)` days

C

`14(5)/(7)` days

D

`13(5)/(7)` days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to determine the work rates of A and B, and then find out how long it will take them to complete the work together. ### Step 1: Determine the total work in terms of units Let's assume the total work is represented by 1 unit. ### Step 2: Calculate A's work rate A can do \( \frac{7}{8} \) of the work in 28 days. Therefore, the amount of work A can do in one day is: \[ \text{Work done by A in one day} = \frac{7/8}{28} = \frac{7}{8 \times 28} = \frac{7}{224} = \frac{1}{32} \text{ units per day} \] ### Step 3: Calculate B's work rate B can do \( \frac{5}{6} \) of the work in 20 days. Therefore, the amount of work B can do in one day is: \[ \text{Work done by B in one day} = \frac{5/6}{20} = \frac{5}{6 \times 20} = \frac{5}{120} = \frac{1}{24} \text{ units per day} \] ### Step 4: Calculate the combined work rate of A and B Now, we can find their combined work rate by adding their individual work rates: \[ \text{Combined work rate} = \text{Work done by A in one day} + \text{Work done by B in one day} = \frac{1}{32} + \frac{1}{24} \] To add these fractions, we need a common denominator. The least common multiple of 32 and 24 is 96. Converting the fractions: \[ \frac{1}{32} = \frac{3}{96} \quad \text{(since } 1 \times 3 = 3 \text{ and } 32 \times 3 = 96\text{)} \] \[ \frac{1}{24} = \frac{4}{96} \quad \text{(since } 1 \times 4 = 4 \text{ and } 24 \times 4 = 96\text{)} \] Now, adding these fractions: \[ \text{Combined work rate} = \frac{3}{96} + \frac{4}{96} = \frac{7}{96} \text{ units per day} \] ### Step 5: Calculate the time taken to complete the work together If A and B work together, they complete \( \frac{7}{96} \) of the work in one day. To find out how many days it will take to complete 1 unit of work, we take the reciprocal of their combined work rate: \[ \text{Time taken} = \frac{1 \text{ unit}}{\frac{7}{96} \text{ units per day}} = \frac{96}{7} \text{ days} \] ### Step 6: Final answer Calculating \( \frac{96}{7} \): \[ \frac{96}{7} \approx 13.71 \text{ days} \] Thus, A and B together will take approximately \( 13.71 \) days to complete the work.
Promotional Banner

Similar Questions

Explore conceptually related problems

A can do (1)/(5)th of a work in 4 days and B can do (1)/(6) th of the same work in 5 days. In how many days they can finish the work, if they work together?

A can do (1)/(3) of a work in 30 days. B can do (2)/(5) of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:

A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

K' can do 3//4^(th) of a work in 6 days and 'I can do 2//5^(th) of the same work in 4 days. How long (in days) will they take, if they work together to finish the work?

If A can do a work in 10 days and B can do the same work in 15 days, then how many days will they take to complete the work both while working together?

A can do 2/5 of a work in 12 days while B can do 66^(2/3)% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in