Home
Class 14
MATHS
Seventy-five men are employed to lay dow...

Seventy-five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time ?

A

300

B

325

C

350

D

375

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will use the concept of man-days, which is a way to measure the amount of work done by a certain number of men in a given number of days. ### Step-by-Step Solution: 1. **Determine the total work in man-days**: - We know that 75 men can complete the work in 3 months. - First, convert months to days. Assuming 1 month = 30 days, then 3 months = 3 × 30 = 90 days. - Therefore, the total work in man-days = Number of men × Number of days = 75 men × 90 days = 6750 man-days. 2. **Calculate the required work to be done in the new time frame**: - The work needs to be completed in 18 days. - Let \( M_2 \) be the number of men required to complete the work in 18 days. - The equation for the total work remains the same: \( M_2 \times 18 \text{ days} = 6750 \text{ man-days} \). 3. **Solve for \( M_2 \)**: - Rearranging the equation gives us \( M_2 = \frac{6750 \text{ man-days}}{18 \text{ days}} \). - Calculating this gives \( M_2 = 375 \text{ men} \). 4. **Determine how many more men are needed**: - Initially, there were 75 men employed. - The additional men required = Total men required - Initial men = \( 375 - 75 = 300 \). ### Final Answer: Therefore, **300 more men should be employed** to complete the work in the desired time of 18 days. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?

Twenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?

20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20