A and B together can do a piece of work in days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone ? `30\ d a y s` b. `40\ d a y s` c. `60\ d a y s` d. `70\ d a y s`

A

30 days

B

40 days

C

60 days

D

70 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • IMO QUESTION PAPER 2019 SET B

    SCIENCE OLYMPIAD FOUNDATION |Exercise ACHIEVERS SECTION |5 Videos
  • IMO QUESTION PAPER 2019 SET B

    SCIENCE OLYMPIAD FOUNDATION |Exercise ACHIEVERS SECTION |5 Videos
  • IMO QUESTION PAPER 2019 SET A

    SCIENCE OLYMPIAD FOUNDATION |Exercise Achievers section|5 Videos
  • IMO QUESTION PAPER 2020 SET 1

    SCIENCE OLYMPIAD FOUNDATION |Exercise Achievers Section|5 Videos

Similar Questions

Explore conceptually related problems

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone ? a. 30 d a y s b. 40 d a y s c. 60 d a y s d. 70 d a y s

X and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in