P and Q each working alone can do a work...

P and Q each working alone can do a work in 10 days and 15 days, respectively. They started the work together but Qleft after sometime and Pfinished the remaining work in 5 days. After how many days from the start did Q leave?

A

3 days

B

6 days

C

2 days

D

4 days

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • CUET MOCK TEST SET 2

    XII BOARDS PREVIOUS YEAR|Exercise MULTIPLE CHOICE QUESTIONS (DATA INTERPRETATION)|5 Videos
  • EXAM REVISION SERIES

    XII BOARDS PREVIOUS YEAR|Exercise All Questions|34 Videos

Similar Questions

Explore conceptually related problems

A and B each working alone can do a work in 15days and 25 days , respectively . They started the work together but B left after some time and A finished the remaining work in 7 days . After how many days from the start did B leave ?

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

A and B can do a piece of work in 10 days and 15 days respectively. They started the work together but B left after sometime and A finished the remaining work in 5 days. After how many days from the start did B leave ?

A and B cand o a pieces of work in 10 days and 15 days, respectively. They started the work together but B left after sometime and A finished the work in 5 days. After how many days (from the start) did B leave?

Raja and Baja working alone can do a work in 20 days and 15 days respectively. They stared the work together but Baja left after sometime and Raja finished remaining work in 6 days. Find after how many days from start Baja left the work?

A and B can do a job in 15 days and 10 days, respectively. They began the work together but A leaves after some days and B finished the remaining job in 5 days. After how many days did A leave?

A and B can do a piece of work in 45 and 40 days respectively. They began the work together, but A leaves after some days and B finished the remaining work in 23 days. After how many days did A leave