6. 12 man to do a job in 90 days . can d...

6. 12 man to do a job in 90 days . can do. 30 when the job starts 2 days after 2 men left work Diya and 8 men joined. remainder How many days will it take to complete the work? (1) 90 days (2) 60 days (3) 40 days (4) 50 days

Promotional Banner

Similar Questions

Explore conceptually related problems

12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

5 men can complete a job in 8 days. How many days will it take if 12 men do the job?

45 men can complete a work in 16 days.Six days after they started working,30 more men joined them.How many days will they now take to complete the remaining work?

A and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone? (A) 30 days (B) 25 days (C) 24 days (D) 15 days

A can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?