A can do a piece of work in 15 days, whi...

A can do a piece of work in 15 days, which B can do in 10 days. B worked at it for 8 days. A can finish the remaining work in `2\ d a y s` b. `3\ d a y s` c. `5\ d a y s` d. `10\ d a y s`