A can do a piece of work in 10 days; B i...

A can do a piece of work in 10 days; B in 15 days. They work for 5 days. The rest of the work was finished by C in 2 days. If they get 1500 for the whole work, the daily wages of B and C are a. Rs. 150 b. `R s .225` c. `R s .250` d. `R s .300`

Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 3000 as wages for the whole work what are the daily wages of A, B and C respectively (in Rs.):

A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and the rest of the work is done by C in 2 days. If they get Rs. 450 for the whole work, how should they divide the money ?

Sunil can do a piece of work in 2 days while Saurav can do it in 3days.They work together for a dayand rest of the work is done by sachin in 1day.If they get 1800 for the whole work,the wage of Sachin is

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and rest of the work is done by M in 2 days. If they get Rs. 9000 for the whole work, then how should they divide the money?

A and B can do a piece of work in 10 days, B and C in 15 days and C and A in 20 days. C alone can do the work in :