4 men and 6 women can complete a work in...

4 men and 6 women can complete a work in 8 days, While 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it.

Text Solution

Verified by Experts

women complete work=x days
Men complete work=y days
Work done by women in 1 day=1/x
Work done by men in 1 dqy=1/y
4 men and 6 women work in 1 day=`4/y+6/x=1/8-(1)`
7 women and 3 men work in 1 day=`7/x+3/y=1/10-(2)`
solving equation 1 and 2
x=400
...
Promotional Banner

Similar Questions

Explore conceptually related problems

9 men and 12 women can complete a work in 4 days, whereas 3 men and 6 women can complete it in 10 days. The numberof days in which 15 women will complete the work is:

4 men and 6 women complete a work in 8 days. 2 men and 9 women also complete in 8 days in which. The number of days in which 18 women complete the work is :

4 men and 6 women finish a job in 8 days, while 3 men and 7 women finish in 10 days. In how many days will 10 women finish it?

In how manu days can the work be done by 9 men and 15 women ? (i) 6 men and 5 women can complete the cork in 6 days. (ii) 3 men and 4 women can complete the work in 10 days (iii) 18 men and 15 women can complete the work in 2 days.

12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

12 men and 15 women can do a work in 6 days, and 6 men and 12 women can do it in 10 days, in how many days can 8 men and 10 women do the same work?

12 men and 16 women can complete a jon in 5 days. 13 men and 24 women can complete the same job in 4 days. How long, in days, will 5 men and 10 women take to complete the same job?