A worker is paid रु 1110 for 6 days.If ...

A worker is paid रु 1110 for 6 days.If his total wages during a month are रु 4625.for how many days he work?

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the unitary method to find out how many days the worker worked based on his total wages. ### Step 1: Find the daily wage of the worker. The worker is paid Rs 1110 for 6 days. To find the daily wage, we divide the total wage by the number of days. \[ \text{Daily Wage} = \frac{\text{Total Wage}}{\text{Number of Days}} = \frac{1110}{6} \] Calculating this gives: \[ \text{Daily Wage} = 185 \] ### Step 2: Find the number of days worked based on total wages. Now we know the daily wage is Rs 185. The total wages for the month are Rs 4625. To find the number of days worked, we divide the total wages by the daily wage. \[ \text{Number of Days Worked} = \frac{\text{Total Wages}}{\text{Daily Wage}} = \frac{4625}{185} \] Calculating this gives: \[ \text{Number of Days Worked} = 25 \] ### Conclusion: The worker worked for **25 days**. ---
Promotional Banner

Topper's Solved these Questions

  • UNITARY METHOD

    RS AGGARWAL|Exercise EXERCISE-9-B|12 Videos
  • UNITARY METHOD

    RS AGGARWAL|Exercise EXERCISE-9-C|16 Videos
  • UNITARY METHOD

    RS AGGARWAL|Exercise EXAMPLE|7 Videos
  • THREE -DIMENSIONAL SHAPES

    RS AGGARWAL|Exercise Execise|1 Videos

Similar Questions

Explore conceptually related problems

A worker is paid Rs 210 for 6 days work. If his total income of the month is Rs 875, for how many days did he work?

A workman is paid Rs 150 for each day he works and is fined Rs50 for each day he is absent.In a month of 30 days he earned Rs 2100. For how many days did he remain absent

Mr. Sahni employed a worker for a certain work to be done in some days. He pays X 20 to the worker for each working day and the payment is red used by X3 for eachnon-working day of the worker.For how many days the worker does remain absent from work if at the end of 120 days, he gets X 560 as total re- muneration?

A, B and C completed a work costing Rs 1800. A worked for 6 days, B worked for 4 days and C worked for 9 days. If their daily wages are in the ratio of 5:6:4, how much amount will be received by A.

A,B and C completes a piece of work costing Rs.1800. A worked for 6 days,B for 4 days and C for 9 days.If their daily wages are in the ratio 5:6:4, how much amount will be recieved by A.

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together ?

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?