A can do a piece of work in 10 days and ...

A can do a piece of work in 10 days and B can do it in 15 days. After they have worked together for 4 days, A does away and B completes the remaining work. In how many days B complete the remaining work ?

A

10

B

5

C

15

D

20

Text Solution

Verified by Experts

The correct Answer is:
B

Find the work done by (A+B) in four days.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away.In how many days will A finish the remaining work?

A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

A can do a piece of work in 25 days and B can finish it in 20 days.They work together for 5 days and then A goes away.In how many days will B finish the remaining work?

PEARSON IIT JEE FOUNDATION-TIME AND WORK, PIPES AND CISTERNS-CONCEPT APPLICATION (LEVEL-1)
  1. A can do (1)/(4)th of a piece of work in one day. While B can do (1)/(...

    Text Solution

    |

  2. A and B can do a piece of work in 50 days and 40 days respectively. If...

    Text Solution

    |

  3. A can do a piece of work in 10 days and B can do it in 15 days. After ...

    Text Solution

    |

  4. A works 3 times as fast as B. If B can complete a work in 60 days, the...

    Text Solution

    |

  5. A and B can do (4)/(5)th and (3)/(5)th of a piece of work in 15 days ...

    Text Solution

    |

  6. Rakesh and Siva can do a piece of work in 15 days and 18 days respecti...

    Text Solution

    |

  7. Twelve men can do a piece of work in 15 days. How many men are require...

    Text Solution

    |

  8. Working individually, A and B can complete a piece of work in 30 days...

    Text Solution

    |

  9. If 4 men or 6 women can do a piece of work in 24 days, then how many m...

    Text Solution

    |

  10. Gauthan and Karthik can do a piece of work in 10 days and 20 days resp...

    Text Solution

    |

  11. P and Q undertook a piece of work for ₹ 37500. P alone can do it in 20...

    Text Solution

    |

  12. A is twice as efficient as B and they together can complete a piece of...

    Text Solution

    |

  13. Two taps A and B can fill a tank in 15 minutes and 20 minutes respecti...

    Text Solution

    |

  14. Malini can do a piece of work in 20 days, while Shalini can do it in 2...

    Text Solution

    |

  15. Working individually, A,B and C can finish a piece of work in 16 days....

    Text Solution

    |

  16. A,B and C can do a piece of work in 12,18 and 9 days respectively. A s...

    Text Solution

    |

  17. Vinay and Varma can do a work in 30 days and 60 days respectively. If ...

    Text Solution

    |

  18. An empty tank can be filled by two pipes individually in 30 minutes an...

    Text Solution

    |

  19. One pipe can fill a tank in 40 minutes and an outlet pipe can empty th...

    Text Solution

    |

  20. A tap can fill an empty tank in 48 minutes whereas another tap can em...

    Text Solution

    |