Twelve men can do a piece of work in 15 ...

Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

A

18

B

54

C

63

D

70

Text Solution

Verified by Experts

The correct Answer is:
C

Use the concept of variation.
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

20 men can do a work in 35 days. How many men are needed to complete the same work in 25 days.

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

10 men can make a wall in 8 days. How many men required to complete the same work in half day

34 men can do a piece of work in 12 days . How many days will 51 men take to do it

24 men can do a piece of work in 17 days. How many men will be able to do it in 51 days?

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?

PEARSON IIT JEE FOUNDATION-TIME AND WORK, PIPES AND CISTERNS-CONCEPT APPLICATION (LEVEL-1)
  1. A and B can do (4)/(5)th and (3)/(5)th of a piece of work in 15 days ...

    Text Solution

    |

  2. Rakesh and Siva can do a piece of work in 15 days and 18 days respecti...

    Text Solution

    |

  3. Twelve men can do a piece of work in 15 days. How many men are require...

    Text Solution

    |

  4. Working individually, A and B can complete a piece of work in 30 days...

    Text Solution

    |

  5. If 4 men or 6 women can do a piece of work in 24 days, then how many m...

    Text Solution

    |

  6. Gauthan and Karthik can do a piece of work in 10 days and 20 days resp...

    Text Solution

    |

  7. P and Q undertook a piece of work for ₹ 37500. P alone can do it in 20...

    Text Solution

    |

  8. A is twice as efficient as B and they together can complete a piece of...

    Text Solution

    |

  9. Two taps A and B can fill a tank in 15 minutes and 20 minutes respecti...

    Text Solution

    |

  10. Malini can do a piece of work in 20 days, while Shalini can do it in 2...

    Text Solution

    |

  11. Working individually, A,B and C can finish a piece of work in 16 days....

    Text Solution

    |

  12. A,B and C can do a piece of work in 12,18 and 9 days respectively. A s...

    Text Solution

    |

  13. Vinay and Varma can do a work in 30 days and 60 days respectively. If ...

    Text Solution

    |

  14. An empty tank can be filled by two pipes individually in 30 minutes an...

    Text Solution

    |

  15. One pipe can fill a tank in 40 minutes and an outlet pipe can empty th...

    Text Solution

    |

  16. A tap can fill an empty tank in 48 minutes whereas another tap can em...

    Text Solution

    |

  17. Two taps A and B can fill a tank in 10 hours and 40 hours respectively...

    Text Solution

    |

  18. Nitu alone can complete (4)/(5)th of a piece of work in 20 days. She w...

    Text Solution

    |

  19. A and B can complete a piece of work in 12 days and 24 days respectivl...

    Text Solution

    |

  20. A can do one-third of a piece of work in 4 days and B can do one-fourt...

    Text Solution

    |