Home
Class 8
MATHS
Malini can do a piece of work in 20 days...

Malini can do a piece of work in 20 days, while Shalini can do it in 25 days. Shalini started the work and after 5 days Malini joined her.They together completed the remaining work. How ,many days did they take to complete the whole work?

A

`8(1)/(8)`

B

8

C

`8(8)/(9)`

D

`13(8)/(9)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by Malini and Shalini individually, then calculate the work done by Shalini in the first 5 days, and finally find out how long it takes for both of them to complete the remaining work together. ### Step 1: Determine the work done by Malini and Shalini in one day. - Malini can complete the work in 20 days. Therefore, her one day work is: \[ \text{Malini's one day work} = \frac{1}{20} \text{ of the work} \] - Shalini can complete the work in 25 days. Therefore, her one day work is: \[ \text{Shalini's one day work} = \frac{1}{25} \text{ of the work} \] ### Step 2: Calculate the total work done by each in one day. To make calculations easier, let's consider the total work as 100 units. - Malini's one day work: \[ \text{Malini's one day work} = \frac{100}{20} = 5 \text{ units} \] - Shalini's one day work: \[ \text{Shalini's one day work} = \frac{100}{25} = 4 \text{ units} \] ### Step 3: Calculate the work done by Shalini in the first 5 days. Since Shalini works alone for the first 5 days: \[ \text{Work done by Shalini in 5 days} = 5 \times 4 = 20 \text{ units} \] ### Step 4: Calculate the remaining work after 5 days. The total work is 100 units, and Shalini has completed 20 units. Therefore, the remaining work is: \[ \text{Remaining work} = 100 - 20 = 80 \text{ units} \] ### Step 5: Calculate the combined work done by Malini and Shalini in one day. When Malini joins Shalini, they work together: \[ \text{Combined one day work} = \text{Malini's one day work} + \text{Shalini's one day work} = 5 + 4 = 9 \text{ units} \] ### Step 6: Calculate the number of days required to complete the remaining work. To find out how many days they need to finish the remaining 80 units: \[ \text{Days required} = \frac{\text{Remaining work}}{\text{Combined one day work}} = \frac{80}{9} \approx 8.89 \text{ days} \text{ or } 8 \frac{8}{9} \text{ days} \] ### Step 7: Calculate the total time taken to complete the work. The total time taken is the time Shalini worked alone plus the time they worked together: \[ \text{Total time} = 5 \text{ days} + \frac{80}{9} \text{ days} = 5 + 8 \frac{8}{9} = 13 \frac{8}{9} \text{ days} \] ### Final Answer: Thus, the total number of days taken to complete the whole work is: \[ \text{Total days} = 13 \frac{8}{9} \text{ days} \] ---

To solve the problem step by step, we will first determine the work done by Malini and Shalini individually, then calculate the work done by Shalini in the first 5 days, and finally find out how long it takes for both of them to complete the remaining work together. ### Step 1: Determine the work done by Malini and Shalini in one day. - Malini can complete the work in 20 days. Therefore, her one day work is: \[ \text{Malini's one day work} = \frac{1}{20} \text{ of the work} \] - Shalini can complete the work in 25 days. Therefore, her one day work is: ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?

A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?

A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working together they will complete the whole work?

PEARSON IIT JEE FOUNDATION-TIME AND WORK, PIPES AND CISTERNS-CONCEPT APPLICATION (LEVEL-1)
  1. A is twice as efficient as B and they together can complete a piece of...

    Text Solution

    |

  2. Two taps A and B can fill a tank in 15 minutes and 20 minutes respecti...

    Text Solution

    |

  3. Malini can do a piece of work in 20 days, while Shalini can do it in 2...

    Text Solution

    |

  4. Working individually, A,B and C can finish a piece of work in 16 days....

    Text Solution

    |

  5. A,B and C can do a piece of work in 12,18 and 9 days respectively. A s...

    Text Solution

    |

  6. Vinay and Varma can do a work in 30 days and 60 days respectively. If ...

    Text Solution

    |

  7. An empty tank can be filled by two pipes individually in 30 minutes an...

    Text Solution

    |

  8. One pipe can fill a tank in 40 minutes and an outlet pipe can empty th...

    Text Solution

    |

  9. A tap can fill an empty tank in 48 minutes whereas another tap can em...

    Text Solution

    |

  10. Two taps A and B can fill a tank in 10 hours and 40 hours respectively...

    Text Solution

    |

  11. Nitu alone can complete (4)/(5)th of a piece of work in 20 days. She w...

    Text Solution

    |

  12. A and B can complete a piece of work in 12 days and 24 days respectivl...

    Text Solution

    |

  13. A can do one-third of a piece of work in 4 days and B can do one-fourt...

    Text Solution

    |

  14. 6 men and 4 women can do a piece of work in 32 days. 7 men and 12 wome...

    Text Solution

    |

  15. Nimai and Gaurang can complete a piece of work in 40 days and 60 days ...

    Text Solution

    |

  16. Two taps A and B can fill a tank in 10 minutes and 15 minutes respect...

    Text Solution

    |

  17. A certain number of people can complete can complete a piece of work i...

    Text Solution

    |

  18. The ratio of the rate of work done for a woman and a man is 2:1. Six w...

    Text Solution

    |

  19. A and B together can do a piece of work in 10 days. If A alone can do ...

    Text Solution

    |

  20. X can do a piece of work in 6 days while Y can do the same work in 8 ...

    Text Solution

    |