Home
Class 8
MATHS
P,Q and R can complete a job in 18 days,...

P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

A

12

B

18

C

4

D

27

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find out how much work P, Q, and R can do individually in one day, and then calculate how much work is completed by each of them during their working days. ### Step 1: Calculate the total work Assume the total work is 216 units (this is a common multiple of the days taken by P, Q, and R). ### Step 2: Calculate the work done by P in one day P can complete the work in 18 days, so the work done by P in one day is: \[ \text{Work done by P in one day} = \frac{216 \text{ units}}{18 \text{ days}} = 12 \text{ units/day} \] ### Step 3: Calculate the work done by P in 3 days In 3 days, P will complete: \[ \text{Work done by P in 3 days} = 12 \text{ units/day} \times 3 \text{ days} = 36 \text{ units} \] ### Step 4: Calculate the remaining work after P's contribution The remaining work after P has worked for 3 days is: \[ \text{Remaining work} = 216 \text{ units} - 36 \text{ units} = 180 \text{ units} \] ### Step 5: Calculate the work done by Q in one day Q can complete the work in 24 days, so the work done by Q in one day is: \[ \text{Work done by Q in one day} = \frac{216 \text{ units}}{24 \text{ days}} = 9 \text{ units/day} \] ### Step 6: Calculate the work done by Q in 8 days In 8 days, Q will complete: \[ \text{Work done by Q in 8 days} = 9 \text{ units/day} \times 8 \text{ days} = 72 \text{ units} \] ### Step 7: Calculate the remaining work after Q's contribution The remaining work after Q has worked for 8 days is: \[ \text{Remaining work} = 180 \text{ units} - 72 \text{ units} = 108 \text{ units} \] ### Step 8: Calculate the work done by R in one day R can complete the work in 36 days, so the work done by R in one day is: \[ \text{Work done by R in one day} = \frac{216 \text{ units}}{36 \text{ days}} = 6 \text{ units/day} \] ### Step 9: Calculate the time taken by R to complete the remaining work To find out how many days R takes to complete the remaining 108 units, we use the formula: \[ \text{Time taken by R} = \frac{\text{Remaining work}}{\text{Work done by R in one day}} = \frac{108 \text{ units}}{6 \text{ units/day}} = 18 \text{ days} \] ### Final Answer R worked for **18 days** to complete the remaining part of the job. ---

To solve the problem, we need to find out how much work P, Q, and R can do individually in one day, and then calculate how much work is completed by each of them during their working days. ### Step 1: Calculate the total work Assume the total work is 216 units (this is a common multiple of the days taken by P, Q, and R). ### Step 2: Calculate the work done by P in one day P can complete the work in 18 days, so the work done by P in one day is: \[ ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

P,Q and R can complete a job in 20 days, 30 and 40 days respectiely. They started working on it. Q and R left afte working for certain number of days and P alone completed the remaing work 7 days. Find the time taken to complete the job (in days)

A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :

A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days. respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is :

P,Q and R can complete a job in 6 days, 9 days and 12 days, respectively. They worked together and completed it. They earned a total of Rs. 2600. Find P's share ( in Rs.)