Home
Class 8
MATHS
A,B and C can do a piece of work in 12,1...

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A

5

B

4

C

3

D

6

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by A, B, and C in one day, then calculate the total work done by A and B, and finally find out how many days C will take to complete the remaining work. ### Step-by-Step Solution: 1. **Determine the Work Rates**: - A can complete the work in 12 days, so A's one day work = \( \frac{1}{12} \). - B can complete the work in 18 days, so B's one day work = \( \frac{1}{18} \). - C can complete the work in 9 days, so C's one day work = \( \frac{1}{9} \). 2. **Calculate Work Done by A in 4 Days**: - Work done by A in 4 days = \( 4 \times \frac{1}{12} = \frac{4}{12} = \frac{1}{3} \). 3. **Calculate Work Done by B in 2 Days**: - Work done by B in 2 days = \( 2 \times \frac{1}{18} = \frac{2}{18} = \frac{1}{9} \). 4. **Calculate Total Work Done by A and B**: - Total work done by A and B = Work done by A + Work done by B - Total work = \( \frac{1}{3} + \frac{1}{9} \). - To add these fractions, find a common denominator (which is 9): - \( \frac{1}{3} = \frac{3}{9} \) - So, \( \frac{1}{3} + \frac{1}{9} = \frac{3}{9} + \frac{1}{9} = \frac{4}{9} \). 5. **Calculate Remaining Work**: - Total work = 1 (the whole work). - Remaining work = Total work - Work done by A and B - Remaining work = \( 1 - \frac{4}{9} = \frac{5}{9} \). 6. **Calculate Days Required by C to Complete Remaining Work**: - C's one day work = \( \frac{1}{9} \). - Let \( x \) be the number of days C will take to complete the remaining work. - Work done by C in \( x \) days = \( x \times \frac{1}{9} \). - Set this equal to the remaining work: - \( x \times \frac{1}{9} = \frac{5}{9} \). - Multiply both sides by 9: - \( x = 5 \). ### Final Answer: C will take **5 days** to complete the remaining work.

To solve the problem step by step, we will first determine the work done by A, B, and C in one day, then calculate the total work done by A and B, and finally find out how many days C will take to complete the remaining work. ### Step-by-Step Solution: 1. **Determine the Work Rates**: - A can complete the work in 12 days, so A's one day work = \( \frac{1}{12} \). - B can complete the work in 18 days, so B's one day work = \( \frac{1}{18} \). - C can complete the work in 9 days, so C's one day work = \( \frac{1}{9} \). ...
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-2)|20 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos
  • TIME AND WORK PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise Essay Type Question|5 Videos
  • TIME AND DISTANCE

    PEARSON IIT JEE FOUNDATION|Exercise Concept Application (Level 2 )|3 Videos
  • TIME AND WORK, PIPES AND CISTERNS

    PEARSON IIT JEE FOUNDATION|Exercise CONCEPT APPLICATION (LEVEL-3)|7 Videos

Similar Questions

Explore conceptually related problems

A,B and C can do a piece of work in 15,12 and 20 days respectively.They started the work together,but C left after 2 days.In how many days will the remaining work be completed by A and B?

A, b and C can alone complete a work in 10, 12 and 15 days respectively. A and C started the work and after working for 4 days, A left and B joined. In how many days the total work was completed ?

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

A can complete of a work in 8 days. B can complete 3/5 of the same work in 12 days and C can complete 4/9 of the same work in 8 days. A and B worked together for 5 days. How much time(in days) will C alone take to complete the remaining work?

A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

A and B can do a job in 16 days and 12 days respectively. B has started the work alone 4 days before finishing the job, A joins B. How many days has B worked alone?

PEARSON IIT JEE FOUNDATION-TIME AND WORK PIPES AND CISTERNS-CONCEPT APPLICATION (LEVEL-1)
  1. Two taps A and B can fill a tank in 15 minutes and 20 minutes respecti...

    Text Solution

    |

  2. Malini can do a piece of work in 20 days, while Shalini can do it in 2...

    Text Solution

    |

  3. Working individually, A,B and C can finish a piece of work in 16 days....

    Text Solution

    |

  4. A,B and C can do a piece of work in 12,18 and 9 days respectively. A s...

    Text Solution

    |

  5. Vinay and Varma can do a work in 30 days and 60 days respectively. If ...

    Text Solution

    |

  6. An empty tank can be filled by two pipes individually in 30 minutes an...

    Text Solution

    |

  7. One pipe can fill a tank in 40 minutes and an outlet pipe can empty th...

    Text Solution

    |

  8. A tap can fill a tank in 48 minutes whereas another tap can empty i...

    Text Solution

    |

  9. Two taps A and B can fill a tank in 10 hours and 40 hours respectively...

    Text Solution

    |

  10. Nitu alone can complete (4)/(5)th of a piece of work in 20 days. She w...

    Text Solution

    |

  11. A and B can complete a piece of work in 12 days and 24 days respectivl...

    Text Solution

    |

  12. A can do one-third of a piece of work in 4 days and B can do one-fourt...

    Text Solution

    |

  13. Six men and 4 women can do a piece of work in 32 days. Seven men and 1...

    Text Solution

    |

  14. Nimai and Gaurang can complete a piece of work in 40 days and 60 days ...

    Text Solution

    |

  15. Two students A and B can finish solving some set of questions in 10 m...

    Text Solution

    |

  16. A certain number of people can complete can complete a piece of work i...

    Text Solution

    |

  17. The ratio of the rate of work done for a woman and a man is 2:1. Six w...

    Text Solution

    |

  18. A and B together can do a piece of work in 10 days. If A alone can do ...

    Text Solution

    |

  19. X can do a piece of work in 6 days while Y can do the same work in 8 ...

    Text Solution

    |

  20. Thirty men can do a piece of work in 16 days working 8 hours a day. Ho...

    Text Solution

    |