A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?

A

`1/6`

B

`1/9`

C

`2/5`

D

`2/7`

Text Solution

Verified by Experts

The correct Answer is:
A
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.

A can complete a work in 18 hours and B can complete the same work in half of his time.If they start working together then how much part will the complete in one day?

Knowledge Check

  • A can finish a work in 18 days and B can do the same work in half the time taken by A. Then working together what part of the same work they can finish in a day?

    A
    `(1)/(6)`
    B
    `(2)/(5)`
    C
    `(1)/(9)`
    D
    `(2)/(7)`
  • X can complete a work in 27 days and Y can do the same work in half of the time taken by X Working together what part of the same work can they complete in a day?

    A
    A)`(1)/(9)`
    B
    B)`(1)/(6)`
    C
    C)`(1)/(12)`
    D
    D)`(2)/(27)`
  • X can complete a work in 27 days and Y can do the same work in half of the time taken by X. Working together what part of the same work can they complete in a day?

    A
    `1//9`
    B
    `1//6`
    C
    `1//12`
    D
    `2//27`
  • Similar Questions

    Explore conceptually related problems

    A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

    A can finish a work in 18 days and B can do the same work in half the time taken by A. What part of the same work can they finish in a day, working together ?

    A can complete a piece of work in 6 days while B can complete the same work in 12 days. If they work together and complete it then, the portion of the work done by A is

    Rahul can complete a work in 18 days and Sonu can complete the same work in 15 days. If both together work for 5 days, then what part of total work is left?