A can do `1/2` of the work in 5 days and B can do `2/5` of the weak in 10 days .in how many days both A and B together can do the work ?

A

`7 (2)/(7) days `

B

`7(1)/(7) days `

C

`7 (3)/(7) days `

D

`7(5)/(7) days `

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how long it will take for A and B to complete the work together. Let's break it down step by step: ### Step 1: Determine the Work Done by A A can do \( \frac{1}{2} \) of the work in 5 days. To find A's efficiency (work done per day), we calculate: \[ \text{Efficiency of A} = \frac{\text{Work}}{\text{Time}} = \frac{\frac{1}{2}}{5} = \frac{1}{10} \] This means A can complete \( \frac{1}{10} \) of the work in one day. ### Step 2: Determine the Work Done by B B can do \( \frac{2}{5} \) of the work in 10 days. To find B's efficiency, we calculate: \[ \text{Efficiency of B} = \frac{\text{Work}}{\text{Time}} = \frac{\frac{2}{5}}{10} = \frac{2}{50} = \frac{1}{25} \] This means B can complete \( \frac{1}{25} \) of the work in one day. ### Step 3: Combine the Efficiencies of A and B Now, we add the efficiencies of A and B to find their combined efficiency: \[ \text{Combined Efficiency} = \text{Efficiency of A} + \text{Efficiency of B} = \frac{1}{10} + \frac{1}{25} \] To add these fractions, we need a common denominator. The least common multiple of 10 and 25 is 50. \[ \frac{1}{10} = \frac{5}{50} \quad \text{and} \quad \frac{1}{25} = \frac{2}{50} \] So, \[ \text{Combined Efficiency} = \frac{5}{50} + \frac{2}{50} = \frac{7}{50} \] ### Step 4: Calculate the Time Taken to Complete the Work Together The time taken to complete the entire work when A and B work together is the inverse of their combined efficiency: \[ \text{Time} = \frac{1}{\text{Combined Efficiency}} = \frac{1}{\frac{7}{50}} = \frac{50}{7} \] This can be expressed as: \[ \frac{50}{7} \text{ days} \approx 7 \frac{1}{7} \text{ days} \] ### Final Answer Thus, A and B together can complete the work in \( \frac{50}{7} \) days or approximately \( 7 \frac{1}{7} \) days. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A can do 1//6 of a work in 5 days and B can do 2/5 of the work in 8 days. In how many days can both A and B together do the work? (A) 12 days (B) 13 days (C ) 15 days (D) 20 days

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A can do a work in 20 days and B can do the same work in 30 days. In how many days, can A and B together do the work? (A) 10 (B) 12 (C) 15 (D) 16

A can do (1)/(5)th of a work in 4 days and B can do (1)/(6) th of the same work in 5 days. In how many days they can finish the work, if they work together?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 ...

    Text Solution

    |

  2. A' can do a piece of work in x days and B can do the same work 3x days...

    Text Solution

    |

  3. A can do 1/2 of the work in 5 days and B can do 2/5 of the weak in 10 ...

    Text Solution

    |

  4. A can do a piece of work in 4 days and B can complete the same work in...

    Text Solution

    |

  5. A can do a piece of work in 8 days, B can do it in 10 days and C can d...

    Text Solution

    |

  6. A, B and C can complete a work in 2h. If A does the job alone in 6h a...

    Text Solution

    |

  7. A and B can do a piece of work in 18 days. B and C in 24 days, C and A...

    Text Solution

    |

  8. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  9. A and B can do piece of work in 10h. B and C can do it in 15h , while ...

    Text Solution

    |

  10. A can do a piece of work in 10 days and B in 20 days. They begin toget...

    Text Solution

    |

  11. A and B together can complete a work in 3 days. They started together ...

    Text Solution

    |

  12. A can do a piece of work in 10 days, while B can do it in 6 days.B wor...

    Text Solution

    |

  13. A and B can complete a job in 24 days working together. A alone can co...

    Text Solution

    |

  14. A contractor undertook to do a certain piece of work in 18 days. He em...

    Text Solution

    |

  15. P and Q can finish a work in 30 days. They worked at it for 10 days an...

    Text Solution

    |

  16. A and B can do a piece of work in 60 days and 75 days, respectively. B...

    Text Solution

    |

  17. A can do a piece of work in 25 days and B can finish it in 20 days. Th...

    Text Solution

    |

  18. A and B can complete a work in 8 days , working together , B alone can...

    Text Solution

    |

  19. 10 men can make a wall in 8 days. How many men required to complete th...

    Text Solution

    |

  20. 6 boys can complete a piece of work in 16 h . In how many will 8 boys ...

    Text Solution

    |