A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. The whole work will be done in?

A

8 days

B

`7 (2)/(3)` days

C

7 days

D

6 days

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 10 days while B can do it in 15 days. They begin together but 5 days before the completion of the work, B leaves off. Find the total number of days for the work to be completed .

A can do a piece of work in 18 days and B in 12 days. They began the work together, but B left the work 3 days before its completion. In how many days, in all, was the work completed ?

A and B can do a piece of work together in 15 days while A alone can do it in 25 days. They start working together but B leaves 5 days before the completion of the work. For how many days did A and B work together?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 10 days,B in 12 days and C in 15 days.All begin together but A leaves the work after 2 days and B leaves 3 days before the work is finished.How long did the work last?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. A and B can do a piece of work in 72 days, B and C can do it in 120 da...

    Text Solution

    |

  2. A and B can do piece of work in 10h. B and C can do it in 15h , while ...

    Text Solution

    |

  3. A can do a piece of work in 10 days and B in 20 days. They begin toget...

    Text Solution

    |

  4. A and B together can complete a work in 3 days. They started together ...

    Text Solution

    |

  5. A can do a piece of work in 10 days, while B can do it in 6 days.B wor...

    Text Solution

    |

  6. A and B can complete a job in 24 days working together. A alone can co...

    Text Solution

    |

  7. A contractor undertook to do a certain piece of work in 18 days. He em...

    Text Solution

    |

  8. P and Q can finish a work in 30 days. They worked at it for 10 days an...

    Text Solution

    |

  9. A and B can do a piece of work in 60 days and 75 days, respectively. B...

    Text Solution

    |

  10. A can do a piece of work in 25 days and B can finish it in 20 days. Th...

    Text Solution

    |

  11. A and B can complete a work in 8 days , working together , B alone can...

    Text Solution

    |

  12. 10 men can make a wall in 8 days. How many men required to complete th...

    Text Solution

    |

  13. 6 boys can complete a piece of work in 16 h . In how many will 8 boys ...

    Text Solution

    |

  14. In a hostel, there are 120 students and food stock is for 45 days. If ...

    Text Solution

    |

  15. If 5 boys take 7 h to pack 35 toys, how many boys can pack 65 toys in ...

    Text Solution

    |

  16. 20 women can complete a piece of work in 7 days. If 8 more women are p...

    Text Solution

    |

  17. 12 men can do a piece of work in 24 days. How many days are needed ...

    Text Solution

    |

  18. 20 men can cut 30 trees in 4 h. If 4 men leave the job, how many trees...

    Text Solution

    |

  19. 40 men can build a wall 200 m long in 12 days, working 8 h a day. What...

    Text Solution

    |

  20. If m men working m hr per day, can do m units of work in m days, then ...

    Text Solution

    |