Home
Class 14
MATHS
A and B together can complete a work in ...

A and B together can complete a work in 3 days. They started together but after 2 days, B left the work. If the work is completed after 2 more days, Balone could do the work in how many days?

A

5

B

6

C

7

D

10

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the combined work rate of A and B A and B together can complete the work in 3 days. Therefore, their combined work rate (efficiency) is: \[ \text{Efficiency of A and B (E_{AB})} = \frac{1}{3} \text{ (work per day)} \] **Hint:** Remember that if they can complete the work in \( n \) days, their combined efficiency is \( \frac{1}{n} \). ### Step 2: Calculate the work done by A and B in 2 days In 2 days, the amount of work done by A and B together is: \[ \text{Work done in 2 days} = 2 \times E_{AB} = 2 \times \frac{1}{3} = \frac{2}{3} \] **Hint:** Multiply the daily work rate by the number of days worked to find the total work done. ### Step 3: Determine the remaining work The total work is considered as 1 unit. After 2 days of work, the remaining work is: \[ \text{Remaining work} = 1 - \frac{2}{3} = \frac{1}{3} \] **Hint:** Subtract the work done from the total work to find the remaining work. ### Step 4: Find the work done by A alone in the next 2 days After B leaves, A continues to work alone for 2 more days to complete the remaining work. Since the remaining work is \( \frac{1}{3} \), we can express A's efficiency as: \[ \text{Let A's efficiency (E_A)} = \frac{1}{x} \text{ (where x is the number of days A takes to complete the work alone)} \] In 2 days, A does: \[ \text{Work done by A in 2 days} = 2 \times E_A \] Setting this equal to the remaining work: \[ 2 \times E_A = \frac{1}{3} \] Thus, \[ E_A = \frac{1}{6} \text{ (work per day)} \] **Hint:** To find A's efficiency, divide the remaining work by the time taken to complete it. ### Step 5: Calculate B's efficiency Now we know: \[ E_{AB} = E_A + E_B \] Substituting the known values: \[ \frac{1}{3} = \frac{1}{6} + E_B \] To find \( E_B \): \[ E_B = \frac{1}{3} - \frac{1}{6} \] Finding a common denominator (6): \[ E_B = \frac{2}{6} - \frac{1}{6} = \frac{1}{6} \] **Hint:** When subtracting fractions, ensure you have a common denominator. ### Step 6: Calculate the time taken by B to complete the work alone Since \( E_B = \frac{1}{6} \), the time taken by B to complete the work alone is: \[ \text{Time taken by B} = \frac{1}{E_B} = \frac{1}{\frac{1}{6}} = 6 \text{ days} \] **Hint:** The time taken to complete the work alone is the reciprocal of the efficiency. ### Final Answer B alone could complete the work in **6 days**. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

A,B and C together can complete a piece of work in 10 days.All the three started working at it together and after 4 days A left.Then B and C completed the work in 10 more days.A alone could complete the work in : a.15 days b.16 days c.25 days d.50 days

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. A and B can do piece of work in 10h. B and C can do it in 15h , while ...

    Text Solution

    |

  2. A can do a piece of work in 10 days and B in 20 days. They begin toget...

    Text Solution

    |

  3. A and B together can complete a work in 3 days. They started together ...

    Text Solution

    |

  4. A can do a piece of work in 10 days, while B can do it in 6 days.B wor...

    Text Solution

    |

  5. A and B can complete a job in 24 days working together. A alone can co...

    Text Solution

    |

  6. A contractor undertook to do a certain piece of work in 18 days. He em...

    Text Solution

    |

  7. P and Q can finish a work in 30 days. They worked at it for 10 days an...

    Text Solution

    |

  8. A and B can do a piece of work in 60 days and 75 days, respectively. B...

    Text Solution

    |

  9. A can do a piece of work in 25 days and B can finish it in 20 days. Th...

    Text Solution

    |

  10. A and B can complete a work in 8 days , working together , B alone can...

    Text Solution

    |

  11. 10 men can make a wall in 8 days. How many men required to complete th...

    Text Solution

    |

  12. 6 boys can complete a piece of work in 16 h . In how many will 8 boys ...

    Text Solution

    |

  13. In a hostel, there are 120 students and food stock is for 45 days. If ...

    Text Solution

    |

  14. If 5 boys take 7 h to pack 35 toys, how many boys can pack 65 toys in ...

    Text Solution

    |

  15. 20 women can complete a piece of work in 7 days. If 8 more women are p...

    Text Solution

    |

  16. 12 men can do a piece of work in 24 days. How many days are needed ...

    Text Solution

    |

  17. 20 men can cut 30 trees in 4 h. If 4 men leave the job, how many trees...

    Text Solution

    |

  18. 40 men can build a wall 200 m long in 12 days, working 8 h a day. What...

    Text Solution

    |

  19. If m men working m hr per day, can do m units of work in m days, then ...

    Text Solution

    |

  20. 20 men complete one- third of a piece of work in 20 days. How many ...

    Text Solution

    |