A and B can complete a work in 8 days , ...

A and B can complete a work in 8 days , working together , B alone can do it in 12 days . After working for 4 days,Bleft the work. How many days willAtake to complete the remaining work?

A

16 days

B

18 days

C

20 days

D

22 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these calculations: ### Step 1: Determine the total work in terms of units A and B can complete the work together in 8 days. Therefore, their combined work rate is: \[ \text{Work rate of A and B together} = \frac{1 \text{ work}}{8 \text{ days}} = \frac{1}{8} \text{ work per day} \] ### Step 2: Determine B's work rate B alone can complete the work in 12 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1 \text{ work}}{12 \text{ days}} = \frac{1}{12} \text{ work per day} \] ### Step 3: Determine A's work rate To find A's work rate, we can use the combined work rate: \[ \text{Work rate of A} = \text{Work rate of A and B} - \text{Work rate of B} \] \[ \text{Work rate of A} = \frac{1}{8} - \frac{1}{12} \] To subtract these fractions, we need a common denominator. The LCM of 8 and 12 is 24. \[ \frac{1}{8} = \frac{3}{24}, \quad \frac{1}{12} = \frac{2}{24} \] \[ \text{Work rate of A} = \frac{3}{24} - \frac{2}{24} = \frac{1}{24} \text{ work per day} \] ### Step 4: Calculate the work done by A and B in 4 days When A and B work together for 4 days, the amount of work they complete is: \[ \text{Work done in 4 days} = 4 \times \text{Work rate of A and B} \] \[ \text{Work done in 4 days} = 4 \times \frac{1}{8} = \frac{4}{8} = \frac{1}{2} \text{ work} \] ### Step 5: Calculate the remaining work Since the total work is 1, the remaining work after B leaves is: \[ \text{Remaining work} = 1 - \frac{1}{2} = \frac{1}{2} \text{ work} \] ### Step 6: Calculate the time taken by A to complete the remaining work Now, we need to find out how long it will take A to complete the remaining work: \[ \text{Time taken by A} = \frac{\text{Remaining work}}{\text{Work rate of A}} \] \[ \text{Time taken by A} = \frac{\frac{1}{2}}{\frac{1}{24}} = \frac{1}{2} \times 24 = 12 \text{ days} \] ### Conclusion Thus, A will take **12 days** to complete the remaining work after B leaves.
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?

A and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. A and B can do a piece of work in 60 days and 75 days, respectively. B...

    Text Solution

    |

  2. A can do a piece of work in 25 days and B can finish it in 20 days. Th...

    Text Solution

    |

  3. A and B can complete a work in 8 days , working together , B alone can...

    Text Solution

    |

  4. 10 men can make a wall in 8 days. How many men required to complete th...

    Text Solution

    |

  5. 6 boys can complete a piece of work in 16 h . In how many will 8 boys ...

    Text Solution

    |

  6. In a hostel, there are 120 students and food stock is for 45 days. If ...

    Text Solution

    |

  7. If 5 boys take 7 h to pack 35 toys, how many boys can pack 65 toys in ...

    Text Solution

    |

  8. 20 women can complete a piece of work in 7 days. If 8 more women are p...

    Text Solution

    |

  9. 12 men can do a piece of work in 24 days. How many days are needed ...

    Text Solution

    |

  10. 20 men can cut 30 trees in 4 h. If 4 men leave the job, how many trees...

    Text Solution

    |

  11. 40 men can build a wall 200 m long in 12 days, working 8 h a day. What...

    Text Solution

    |

  12. If m men working m hr per day, can do m units of work in m days, then ...

    Text Solution

    |

  13. 20 men complete one- third of a piece of work in 20 days. How many ...

    Text Solution

    |

  14. 15 men complete a work in 16 days. If 24 men are employed, then the ti...

    Text Solution

    |

  15. 20 workers working for 5 h per day complete a work in 10 days. If 25 w...

    Text Solution

    |

  16. A certain number of men can do a piece of work in 80 days. If there we...

    Text Solution

    |

  17. A stock of food is enough for 240 men for 48 days. How long will the s...

    Text Solution

    |

  18. 45 people take 18 days to dig a pond. If the pond would have to be dug...

    Text Solution

    |

  19. If 3 men and 4 women can build a wall in 43 days , in how many days ca...

    Text Solution

    |

  20. If 12 men of 18 women can do a work in 14 days, then in how many da...

    Text Solution

    |