40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

A

32

B

18

C

36

D

9

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step-by-step, we will use the formula that relates the number of men (m), days (d), hours per day (h), and work done (w). The formula we will use is: \[ \frac{m_1 \cdot d_1 \cdot h_1}{w_1} = \frac{m_2 \cdot d_2 \cdot h_2}{w_2} \] ### Step 1: Identify the values from the first case From the problem, we have the following values for the first case: - \( m_1 = 40 \) men - \( d_1 = 12 \) days - \( h_1 = 8 \) hours/day - \( w_1 = 200 \) meters (length of the wall) ### Step 2: Identify the values from the second case For the second case, we have: - \( m_2 = 30 \) men - \( d_2 = ? \) (this is what we need to find) - \( h_2 = 6 \) hours/day - \( w_2 = 300 \) meters (length of the wall) ### Step 3: Substitute the values into the formula Now we can substitute the values into the formula: \[ \frac{40 \cdot 12 \cdot 8}{200} = \frac{30 \cdot d_2 \cdot 6}{300} \] ### Step 4: Simplify both sides First, simplify the left side: \[ \frac{40 \cdot 12 \cdot 8}{200} = \frac{3840}{200} = 19.2 \] Now simplify the right side: \[ \frac{30 \cdot d_2 \cdot 6}{300} = \frac{180d_2}{300} = 0.6d_2 \] ### Step 5: Set the two sides equal to each other Now we have: \[ 19.2 = 0.6d_2 \] ### Step 6: Solve for \( d_2 \) To find \( d_2 \), divide both sides by 0.6: \[ d_2 = \frac{19.2}{0.6} = 32 \] ### Conclusion Thus, the number of days that 30 men will take to build a similar wall 300 m long, working 6 hours per day, is **32 days**. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

40 men can build a wall 200 m longin 12 days working 8 h a day. The number of days 30 men will take to build a similar wall 300 m long working 6h per day will be (A) 32 (B) 18 (C) 36 (D) 9

24 workers can build a wall in 15 days. How many days will 9 workers take to build a similar wall?

If 20 men can build a wall 56 metres long in 6 day what length of a similar wall can be built by 35 men in 3 days?

If 24 workers can build a wall in 15 days, how many days will 8 workers take to build a similar wall?

300 men can construct a200m long wall in 12 days working 8 hours a day. In how many days can 120 men construct 180 m long wall working 9 hours per day?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. 12 men can do a piece of work in 24 days. How many days are needed ...

    Text Solution

    |

  2. 20 men can cut 30 trees in 4 h. If 4 men leave the job, how many trees...

    Text Solution

    |

  3. 40 men can build a wall 200 m long in 12 days, working 8 h a day. What...

    Text Solution

    |

  4. If m men working m hr per day, can do m units of work in m days, then ...

    Text Solution

    |

  5. 20 men complete one- third of a piece of work in 20 days. How many ...

    Text Solution

    |

  6. 15 men complete a work in 16 days. If 24 men are employed, then the ti...

    Text Solution

    |

  7. 20 workers working for 5 h per day complete a work in 10 days. If 25 w...

    Text Solution

    |

  8. A certain number of men can do a piece of work in 80 days. If there we...

    Text Solution

    |

  9. A stock of food is enough for 240 men for 48 days. How long will the s...

    Text Solution

    |

  10. 45 people take 18 days to dig a pond. If the pond would have to be dug...

    Text Solution

    |

  11. If 3 men and 4 women can build a wall in 43 days , in how many days ca...

    Text Solution

    |

  12. If 12 men of 18 women can do a work in 14 days, then in how many da...

    Text Solution

    |

  13. In a school , mid day meal food is sufficient for 250 students for 33 ...

    Text Solution

    |

  14. 90 men are engaged to do a piece of work in 40 days but it is found th...

    Text Solution

    |

  15. 36 workmen are employed to finish a certain work in 48 days. But it is...

    Text Solution

    |

  16. It is given that 16men working 18hr per day can build a wall 36m long,...

    Text Solution

    |

  17. 3 men can do a piece of work in 6 days. 5 women can do the same work i...

    Text Solution

    |

  18. 3 men can do a piece of work in 18 days. 6 children can also do that w...

    Text Solution

    |

  19. A man can do a piece of work in 5 days . With the help of his friend ,...

    Text Solution

    |

  20. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |