15 men complete a work in 16 days. If 24...

15 men complete a work in 16 days. If 24 men are employed, then the time required to complete that work will be

A

7 days

B

8 days

C

10 days

D

12 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. If m men working m hr per day, can do m units of work in m days, then ...

    Text Solution

    |

  2. 20 men complete one- third of a piece of work in 20 days. How many ...

    Text Solution

    |

  3. 15 men complete a work in 16 days. If 24 men are employed, then the ti...

    Text Solution

    |

  4. 20 workers working for 5 h per day complete a work in 10 days. If 25 w...

    Text Solution

    |

  5. A certain number of men can do a piece of work in 80 days. If there we...

    Text Solution

    |

  6. A stock of food is enough for 240 men for 48 days. How long will the s...

    Text Solution

    |

  7. 45 people take 18 days to dig a pond. If the pond would have to be dug...

    Text Solution

    |

  8. If 3 men and 4 women can build a wall in 43 days , in how many days ca...

    Text Solution

    |

  9. If 12 men of 18 women can do a work in 14 days, then in how many da...

    Text Solution

    |

  10. In a school , mid day meal food is sufficient for 250 students for 33 ...

    Text Solution

    |

  11. 90 men are engaged to do a piece of work in 40 days but it is found th...

    Text Solution

    |

  12. 36 workmen are employed to finish a certain work in 48 days. But it is...

    Text Solution

    |

  13. It is given that 16men working 18hr per day can build a wall 36m long,...

    Text Solution

    |

  14. 3 men can do a piece of work in 6 days. 5 women can do the same work i...

    Text Solution

    |

  15. 3 men can do a piece of work in 18 days. 6 children can also do that w...

    Text Solution

    |

  16. A man can do a piece of work in 5 days . With the help of his friend ,...

    Text Solution

    |

  17. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  18. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  19. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  20. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |