Home
Class 14
MATHS
90 men are engaged to do a piece of work...

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A

10

B

15

C

20

D

25

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the concept of work done, which is based on the number of men, the number of days, and the total work. ### Step 1: Understand the total work and the work done in the given time. - **Total work (W)** can be calculated based on the initial information. If 90 men can complete the work in 40 days, the total work can be expressed as: \[ W = \text{Men} \times \text{Days} = 90 \times 40 = 3600 \text{ man-days} \] ### Step 2: Calculate the work done in 25 days. - In 25 days, it is given that \( \frac{2}{3} \) of the work is completed. Therefore, the work done in 25 days is: \[ W_1 = \frac{2}{3} \times 3600 = 2400 \text{ man-days} \] ### Step 3: Determine the remaining work. - The remaining work \( W_2 \) can be calculated as: \[ W_2 = W - W_1 = 3600 - 2400 = 1200 \text{ man-days} \] ### Step 4: Calculate the remaining days to complete the work. - Since 25 days have already been used, the remaining days \( D_2 \) to finish the work is: \[ D_2 = 40 - 25 = 15 \text{ days} \] ### Step 5: Set up the equation for the remaining work. - Let \( x \) be the number of men who will go off. The number of men remaining will be \( 90 - x \). The equation for the remaining work can be set up as: \[ (90 - x) \times 15 = 1200 \] ### Step 6: Solve for \( x \). 1. Expand the equation: \[ 1350 - 15x = 1200 \] 2. Rearranging gives: \[ 90 - 15x = 1200 \] 3. Now, isolate \( x \): \[ 15x = 90 - 1200 \] \[ 15x = -1110 \] \[ x = \frac{1110}{15} = 74 \] ### Step 7: Conclusion. - Therefore, the number of men that should be allowed to go off is: \[ x = 74 \]
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

If 56 men can do a piece of work in 42 days. How many men will do it in 14 days?

If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.

A contract is to be completed in 92 days and 234 men set to work , each working 16h a day. After 66 days , 4/7 of the work is completed. How many additional men many be employed , so that the work may be completed in time , each man now working 18h a day ?

A contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it?

24 men can do a piece of work in 17 days. How many men will be able to do it in 51 days?

If 45 men can do a piece of work in 49 days, in how many days will 35 men do it?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. If 12 men of 18 women can do a work in 14 days, then in how many da...

    Text Solution

    |

  2. In a school , mid day meal food is sufficient for 250 students for 33 ...

    Text Solution

    |

  3. 90 men are engaged to do a piece of work in 40 days but it is found th...

    Text Solution

    |

  4. 36 workmen are employed to finish a certain work in 48 days. But it is...

    Text Solution

    |

  5. It is given that 16men working 18hr per day can build a wall 36m long,...

    Text Solution

    |

  6. 3 men can do a piece of work in 6 days. 5 women can do the same work i...

    Text Solution

    |

  7. 3 men can do a piece of work in 18 days. 6 children can also do that w...

    Text Solution

    |

  8. A man can do a piece of work in 5 days . With the help of his friend ,...

    Text Solution

    |

  9. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  10. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  11. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  12. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  13. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  14. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  15. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  16. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  17. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  18. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  19. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  20. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |