36 workmen are employed to finish a cert...

36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?

A

16

B

18

C

20

D

22

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A certain work is to be finished in a month,12 worker appointed upon it could finished one- third of the work only in 12 days.How many additional workers must be employed to finish to the work in time?

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 2/3 of the work. How many men can be discharged now so that the work inay finish in time?

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. In a school , mid day meal food is sufficient for 250 students for 33 ...

    Text Solution

    |

  2. 90 men are engaged to do a piece of work in 40 days but it is found th...

    Text Solution

    |

  3. 36 workmen are employed to finish a certain work in 48 days. But it is...

    Text Solution

    |

  4. It is given that 16men working 18hr per day can build a wall 36m long,...

    Text Solution

    |

  5. 3 men can do a piece of work in 6 days. 5 women can do the same work i...

    Text Solution

    |

  6. 3 men can do a piece of work in 18 days. 6 children can also do that w...

    Text Solution

    |

  7. A man can do a piece of work in 5 days . With the help of his friend ,...

    Text Solution

    |

  8. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  9. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  10. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  11. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  12. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  13. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  14. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  15. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  16. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  17. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  18. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  19. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |

  20. If one man or two women or three boys can finish a work in 88 days, th...

    Text Solution

    |