Home
Class 14
MATHS
It is given that 16men working 18hr per ...

It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?

A

60

B

20

C

30

D

35

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the concept of work done, which can be calculated as the product of the number of men, the number of hours they work per day, and the number of days they work. ### Step 1: Calculate the total work done in the first case The total work done can be calculated using the formula: \[ \text{Work} = \text{Length} \times \text{Breadth} \times \text{Height} \] For the first wall: - Length = 36 m - Breadth = 4 m - Height = 24 m So, the total work done (W1) is: \[ W_1 = 36 \times 4 \times 24 \] ### Step 2: Calculate the total work done in the first case Now, let's calculate \( W_1 \): \[ W_1 = 36 \times 4 \times 24 = 3456 \, \text{m}^3 \] ### Step 3: Calculate the total man-hours in the first case The total man-hours can be calculated as: \[ \text{Total Man-Hours} = \text{Number of Men} \times \text{Hours per Day} \times \text{Days} \] For the first case: - Number of Men (M1) = 16 - Hours per Day (D1) = 18 - Days (T1) = 20 So, the total man-hours (M1) is: \[ M_1 = 16 \times 18 \times 20 \] ### Step 4: Calculate the total man-hours in the first case Now, let's calculate \( M_1 \): \[ M_1 = 16 \times 18 \times 20 = 5760 \, \text{man-hours} \] ### Step 5: Calculate the work done per man-hour Now, we can find the work done per man-hour in the first case: \[ \text{Work per Man-Hour} = \frac{W_1}{M_1} = \frac{3456}{5760} \] ### Step 6: Calculate the work done per man-hour Now, let's calculate: \[ \text{Work per Man-Hour} = \frac{3456}{5760} = 0.6 \, \text{m}^3/\text{man-hour} \] ### Step 7: Calculate the total work required for the second wall For the second wall: - Length = 64 m - Breadth = 6 m - Height = 18 m So, the total work required (W2) is: \[ W_2 = 64 \times 6 \times 18 \] ### Step 8: Calculate the total work required for the second wall Now, let's calculate \( W_2 \): \[ W_2 = 64 \times 6 \times 18 = 6912 \, \text{m}^3 \] ### Step 9: Calculate the total man-hours available in the second case For the second case: - Hours per Day (D2) = 12 - Days (T2) = 16 Now, we need to find the total man-hours (M2): \[ M_2 = \text{Number of Men} \times 12 \times 16 \] ### Step 10: Set up the equation to find the number of men required Let the number of men required be \( x \). Then: \[ x \times 12 \times 16 = \text{Total Work Required} \] ### Step 11: Substitute the values and solve for x Using the work done per man-hour: \[ x \times 12 \times 16 = 6912 \] \[ x \times 192 = 6912 \] \[ x = \frac{6912}{192} \] ### Step 12: Calculate the number of men required Now, let's calculate: \[ x = 36 \] ### Final Answer The number of men required to build the second wall is **36 men**.
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

Four persons can build a wall in 12 days . How many persons will be required to build the same will in 8 days.

15 men can build a 16.25 -m- long wall up to a certainj height in one day. How many men should be employed to build a wall of the same height but of length 26 metres in one day?

40 men build a well 20 m high in 15 days. The number of men required to build a similar wall 25 m high in 6 days will be:

A tank is 8m long,6m broad and 2m high.How much water can it contain?

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. 90 men are engaged to do a piece of work in 40 days but it is found th...

    Text Solution

    |

  2. 36 workmen are employed to finish a certain work in 48 days. But it is...

    Text Solution

    |

  3. It is given that 16men working 18hr per day can build a wall 36m long,...

    Text Solution

    |

  4. 3 men can do a piece of work in 6 days. 5 women can do the same work i...

    Text Solution

    |

  5. 3 men can do a piece of work in 18 days. 6 children can also do that w...

    Text Solution

    |

  6. A man can do a piece of work in 5 days . With the help of his friend ,...

    Text Solution

    |

  7. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  8. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  9. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  10. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  11. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  12. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  13. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  14. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  15. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  16. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  17. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  18. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |

  19. If one man or two women or three boys can finish a work in 88 days, th...

    Text Solution

    |

  20. When A alone does a piece of work , he takes 25 days more than the tim...

    Text Solution

    |