A takes twice as much time as B and C ta...

A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.

A

20

B

22

C

33

D

44

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in : a. 4 days b. 6 d a y s c. 8 d a y s d. 12 d a y s

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A takes 10days less than the time taken by B to finish a piece of work.If both A and B together can finish the work in 12 days,find the time taken by B to finish the work.

A is twice as good as B and together they finish a piece of work in 16 days. The number of days taken by A alone to finish the work is

A is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......

A takes 6 days less than the time taken by B to finish a piece of work.If both A and B together can finish it in 4 days.Find the time taken by B to finish the work.

A takes three times as long as (B + C) together to complete a work. B takes four times as much as (A + C) together to complete a work. If all the three, working together can complete the work in 22 days, then find the number of days A, B and C alone will take to complete this work

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  2. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  3. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  4. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  5. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  6. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  7. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  8. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  9. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  10. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  11. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  12. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |

  13. If one man or two women or three boys can finish a work in 88 days, th...

    Text Solution

    |

  14. When A alone does a piece of work , he takes 25 days more than the tim...

    Text Solution

    |

  15. X can do 1/4 of a work in 10 days, Y can do 40% of the same work in 40...

    Text Solution

    |

  16. Five men are working to complete a work in 1 days. After five days ...

    Text Solution

    |

  17. 4 men or 6 women or 10 children can paint a house in 5 days. The paint...

    Text Solution

    |

  18. 4 goats or 6 sheeps can graze a field in 50 days . 2 goats and 9 sheep...

    Text Solution

    |

  19. If 14 men and 12 boys can finish work in 4 days , while 8 men and 16 b...

    Text Solution

    |

  20. If the work done by 8 men and 4 boys in 1 day is 7 times the work done...

    Text Solution

    |