Home
Class 14
MATHS
A takes twice the time taken by B and th...

A takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone

A

12,6 and 4

B

18,9 and 6

C

24,12 and 8

D

6,3 and 2

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will denote the time taken by B to complete the work alone as \( x \) days. ### Step 1: Define the time taken by A and C According to the problem: - A takes twice the time taken by B, so the time taken by A is \( 2x \) days. - A takes thrice the time taken by C, so the time taken by C can be expressed as \( \frac{2x}{3} \) days. ### Step 2: Calculate the work done by A, B, and C in one day Now we can calculate the work done by each person in one day: - Work done by A in one day = \( \frac{1}{2x} \) - Work done by B in one day = \( \frac{1}{x} \) - Work done by C in one day = \( \frac{3}{2x} \) ### Step 3: Combine the work done by A, B, and C When A, B, and C work together, their combined work done in one day is: \[ \text{Total work in one day} = \frac{1}{2x} + \frac{1}{x} + \frac{3}{2x} \] ### Step 4: Simplify the combined work To combine these fractions, we need a common denominator, which is \( 2x \): \[ \text{Total work in one day} = \frac{1}{2x} + \frac{2}{2x} + \frac{3}{2x} = \frac{1 + 2 + 3}{2x} = \frac{6}{2x} = \frac{3}{x} \] ### Step 5: Set up the equation based on the total work done in 2 days According to the problem, working together they can complete the work in 2 days. Therefore: \[ \text{Total work} = 1 \quad \text{(the whole work)} \] So, the equation becomes: \[ \frac{3}{x} \times 2 = 1 \] This simplifies to: \[ \frac{6}{x} = 1 \] ### Step 6: Solve for x Now, we solve for \( x \): \[ 6 = x \quad \Rightarrow \quad x = 6 \] ### Step 7: Find the time taken by A and C Now that we have \( x \): - Time taken by B = \( x = 6 \) days - Time taken by A = \( 2x = 2 \times 6 = 12 \) days - Time taken by C = \( \frac{2x}{3} = \frac{2 \times 6}{3} = 4 \) days ### Final Answer Thus, the number of days taken by A, B, and C respectively to complete the work alone are: - A: 12 days - B: 6 days - C: 4 days
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together,they can finish the work in 12 days.Find the number of days needed for A to do the work alone.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

Time taken by A to complete a work is 7 days more than the time taken by B to complete the same work. Working together they can complete the work in 12 days. In what time can A alone complete the work ?

Rahul takes twice as such time as Manick and thrice as much time a Sachin a job.If working together,they can complete the job in 4 days, find the time taken by each of them separately to complete the work.

B takes two times as long as (A + C) together to complete a work. C takes three times as much as (A + B) together to complete a work. If all the three, working together can complete the work in 36 days, then find the number of days A, B and C alone will take to complete this work.

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  2. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  3. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  4. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  5. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  6. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  7. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  8. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  9. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  10. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  11. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  12. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |

  13. If one man or two women or three boys can finish a work in 88 days, th...

    Text Solution

    |

  14. When A alone does a piece of work , he takes 25 days more than the tim...

    Text Solution

    |

  15. X can do 1/4 of a work in 10 days, Y can do 40% of the same work in 40...

    Text Solution

    |

  16. Five men are working to complete a work in 1 days. After five days ...

    Text Solution

    |

  17. 4 men or 6 women or 10 children can paint a house in 5 days. The paint...

    Text Solution

    |

  18. 4 goats or 6 sheeps can graze a field in 50 days . 2 goats and 9 sheep...

    Text Solution

    |

  19. If 14 men and 12 boys can finish work in 4 days , while 8 men and 16 b...

    Text Solution

    |

  20. If the work done by 8 men and 4 boys in 1 day is 7 times the work done...

    Text Solution

    |