If 14 men and 12 boys can finish work in 4 days , while 8 men and 16 boys can finish the same work in 5 days . Compare the 1 day work of 1 man and 1 boy .

A

2

B

`1 (1)/(2)`

C

`1/2`

D

`3 `

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find the work done by one man and one boy based on the information provided. Let's break it down step by step. ### Step 1: Understand the given information We have two scenarios: 1. 14 men and 12 boys can finish the work in 4 days. 2. 8 men and 16 boys can finish the same work in 5 days. ### Step 2: Set up the equations Let the work done by one man in one day be \( M \) and the work done by one boy in one day be \( B \). From the first scenario: - Total work done by 14 men and 12 boys in 4 days: \[ \text{Total Work} = (14M + 12B) \times 4 \] From the second scenario: - Total work done by 8 men and 16 boys in 5 days: \[ \text{Total Work} = (8M + 16B) \times 5 \] Since both expressions represent the same total work, we can set them equal to each other: \[ (14M + 12B) \times 4 = (8M + 16B) \times 5 \] ### Step 3: Simplify the equation Expanding both sides: \[ 56M + 48B = 40M + 80B \] ### Step 4: Rearranging the equation Now, we can rearrange the equation to isolate terms involving \( M \) and \( B \): \[ 56M - 40M = 80B - 48B \] \[ 16M = 32B \] ### Step 5: Find the ratio of work done Dividing both sides by 16: \[ M = 2B \] This means the work done by one man in one day is twice the work done by one boy in one day. ### Step 6: Conclusion The comparison of the one day work of one man and one boy is: \[ \text{Work done by 1 man} : \text{Work done by 1 boy} = 2 : 1 \]
Promotional Banner

Topper's Solved these Questions

  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos
  • VOLUME AND SURFACE AREA

    ARIHANT SSC|Exercise FAST TRACK PRACTICE|111 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos

Similar Questions

Explore conceptually related problems

If 12 men and 16 boys can finish a work in 5 days, while 13 men and 24 boys can finish the same work in 4 days. Compare the one day work of 1 man and 1 boy.

If 3 men and 4 boys can do a piece of work in 8 day, then 6 men and 8 boys can do the same work in

4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 boys can finish the same work in 5 days. Also 2 men and 3 women can finish the same work in 5 days. In how many days 1 man, 1 woman and one boy can finish the work, at their double efficiency?

4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is

8 men and 12 boys can finish a piece of work in 5 days, while 6 men and 8 boys can finish it in 7 days. Find the time taken by 1 man along and that by 1 boy alone to finish the work.

2men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days.In how many days can 2 men and 1 boy do the work?

8men and 12 boys can finish a work in 10 days while 6 men and 8 boys can finish it in 14 days.Find the time taken by one man alone and that by one boy alone to finish the work.

8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days.Find the time taken by one man alone and that by one boy alone to finish the work.

2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.

ARIHANT SSC-WORK AND TIME -EXERCISE BASE LEVEL QUESTION
  1. P can do a piece of work in 12 days , while Q alone can finish it in 8...

    Text Solution

    |

  2. A alone can do a certain job in 15 days , while B alone can do it in 1...

    Text Solution

    |

  3. A mason can build a tank in 12 h. After working for 6 h, he took the h...

    Text Solution

    |

  4. A and B can do a job together in 12days . A is 2 times as efficient a...

    Text Solution

    |

  5. 16 children and 24 men complete a certain workin 18days. If each child...

    Text Solution

    |

  6. A does 20% less work than B. If A can finish a piece of work in 7(1)/(...

    Text Solution

    |

  7. A takes twice as much time as B and C take thrice as much time as B to...

    Text Solution

    |

  8. A is thrice as good a workman as B and therefore is able to finish a j...

    Text Solution

    |

  9. X can do a work in 16 days. In how many days will the work be complete...

    Text Solution

    |

  10. 10 men and 8 women together can complete a work in 5 days. Work done b...

    Text Solution

    |

  11. A takes twice the time taken by B and thrice the time taken by C to do...

    Text Solution

    |

  12. X can do 20% of a work in a day , Y can do 25% of the same work in a d...

    Text Solution

    |

  13. If one man or two women or three boys can finish a work in 88 days, th...

    Text Solution

    |

  14. When A alone does a piece of work , he takes 25 days more than the tim...

    Text Solution

    |

  15. X can do 1/4 of a work in 10 days, Y can do 40% of the same work in 40...

    Text Solution

    |

  16. Five men are working to complete a work in 1 days. After five days ...

    Text Solution

    |

  17. 4 men or 6 women or 10 children can paint a house in 5 days. The paint...

    Text Solution

    |

  18. 4 goats or 6 sheeps can graze a field in 50 days . 2 goats and 9 sheep...

    Text Solution

    |

  19. If 14 men and 12 boys can finish work in 4 days , while 8 men and 16 b...

    Text Solution

    |

  20. If the work done by 8 men and 4 boys in 1 day is 7 times the work done...

    Text Solution

    |