A can finish a work in 15 days, B in 20 ...

A can finish a work in 15 days, B in 20 days and C in 25 days. All these three worked together and earned RS. 4700. The share of C is

A

`?1200`

B

`?1500`

C

`?1800`

D

`?2000`

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos

Similar Questions

Explore conceptually related problems

A can finish a work in 15 days, B in 20 days and C in 25 days . All these three worked together and earned Rs. 4,700 . The share of C is

A,B and C can complete a piece of work in 4 day, 8 days, and 12 days, respectively. They worked together and earned a total of Rs. 660. Find the B's share (in rupees)

A, B and C can do a work in x,3x and 5x days, respectively. They worked together and earned Rs. 460. What is the share of B?

A and B can finish a work in 15 days, B and C in 20 days, while C and A in 30 days, then A alone can finish the work in

A and B can do a work in 12 days .B and C in 15 days .C and A in 20 days. If A,B and C work together ,they will complete the work in :

ARIHANT SSC-WORK AND WAGES -EXERCISE BASE LEVEL QUESTIONS
  1. Shantanu can do a piece of work in 12 days and Manu can do the same wo...

    Text Solution

    |

  2. A can do a piece of work in 9 days and B can do the same work in 15 da...

    Text Solution

    |

  3. A man and a boy received Rs.1400 as wages for 10 days for the work the...

    Text Solution

    |

  4. A alone can do a piece of work in 8 days while B alone can do it in 10...

    Text Solution

    |

  5. A can do a piece of work in 3 days while B can do the same work in 4 d...

    Text Solution

    |

  6. A alone can do a piece of work in 3 days, while B alone can do the sam...

    Text Solution

    |

  7. A can finish a work in 15 days, B in 20 days and C in 25 days. All the...

    Text Solution

    |

  8. A person can do a piece of work in 26 days and an another person can d...

    Text Solution

    |

  9. A alone can finish a work in 2 days, while B alone can finish it in 3 ...

    Text Solution

    |

  10. Vandana can do a piece of work in 10 days. With the help of Ruchi, she...

    Text Solution

    |

  11. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  12. Amit, Vipul and Kapil can do a piece of work in 12, 16 and 24 days, re...

    Text Solution

    |

  13. P, Q and R enter into a contract for a piece of work for Rs. 1100. P a...

    Text Solution

    |

  14. Ramesh and Suresh undertaken to do a piece of work for Rs. 800. Ramesh...

    Text Solution

    |

  15. A, B and C completed a work costing Rs 1800. A worked for 6 days, B wo...

    Text Solution

    |

  16. A and B undertaken to do a piece of work for Rs 1200. A alone can do i...

    Text Solution

    |

  17. A, B and C can do a piece of work in 20, 24 and 30 days, respectively....

    Text Solution

    |