Home
Class 14
MATHS
A, B and C can do a piece of work in 20,...

A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is

A

Rs.2700

B

Rs. 540

C

Rs. 1800

D

Rs. 600

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the outlined approach in the video transcript. ### Step 1: Determine the Work Rates of A, B, and C - A can complete the work in 20 days, so A's work rate is \( \frac{1}{20} \) of the work per day. - B can complete the work in 24 days, so B's work rate is \( \frac{1}{24} \) of the work per day. - C can complete the work in 30 days, so C's work rate is \( \frac{1}{30} \) of the work per day. ### Step 2: Find the Total Work To find a common measure for the work done, we can take the least common multiple (LCM) of the days: - The LCM of 20, 24, and 30 is 120. - Therefore, the total work can be assumed to be 120 units. ### Step 3: Calculate Individual Work Contributions Now, we calculate the work done by each person in terms of units: - A's work in 120 units: \( \frac{120}{20} = 6 \) units per day. - B's work in 120 units: \( \frac{120}{24} = 5 \) units per day. - C's work in 120 units: \( \frac{120}{30} = 4 \) units per day. ### Step 4: Calculate Total Work Done Together The combined work done by A, B, and C in one day is: - Total work rate = \( 6 + 5 + 4 = 15 \) units per day. ### Step 5: Determine the Total Time Worked Let’s assume they worked together for \( x \) days. Since B left 2 days before the completion and C left 5 days before the completion, we can express the total work done as: - A worked for \( x \) days. - B worked for \( x - 2 \) days. - C worked for \( x - 5 \) days. The total work can be expressed as: \[ 6x + 5(x - 2) + 4(x - 5) = 120 \] ### Step 6: Simplify the Equation Expanding the equation: \[ 6x + 5x - 10 + 4x - 20 = 120 \] Combining like terms: \[ 15x - 30 = 120 \] Adding 30 to both sides: \[ 15x = 150 \] Dividing by 15: \[ x = 10 \] ### Step 7: Calculate Work Done by Each Person Now we can calculate how much work each person did: - A's work: \( 6 \times 10 = 60 \) units. - B's work: \( 5 \times 8 = 40 \) units (B worked for 8 days). - C's work: \( 4 \times 5 = 20 \) units (C worked for 5 days). ### Step 8: Calculate the Share of A The total work is 120 units, and the payment is Rs. 5400. The share of A can be calculated as follows: \[ \text{Share of A} = \frac{\text{Work done by A}}{\text{Total work}} \times \text{Total payment} \] \[ \text{Share of A} = \frac{60}{120} \times 5400 = \frac{1}{2} \times 5400 = 2700 \] ### Final Answer Thus, the share of A from the assured money is Rs. 2700. ---
Promotional Banner

Topper's Solved these Questions

  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos
  • WORK AND WAGES

    ARIHANT SSC|Exercise EXERCISE (HIGHER SKILL LEVEL QUESTIONS)|7 Videos
  • WORK AND TIME

    ARIHANT SSC|Exercise EXERCISE HIGHER SKILL LEVEL QUESTION|16 Videos

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work but A left 8 days before the completion of the work while B left 12 days before the completion. The number of days for which C worked is a. 4 b. 8 c.12 d. 24

A, B and C can complete a piec of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work in completed ?

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

ARIHANT SSC-WORK AND WAGES -EXERCISE BASE LEVEL QUESTIONS
  1. Shantanu can do a piece of work in 12 days and Manu can do the same wo...

    Text Solution

    |

  2. A can do a piece of work in 9 days and B can do the same work in 15 da...

    Text Solution

    |

  3. A man and a boy received Rs.1400 as wages for 10 days for the work the...

    Text Solution

    |

  4. A alone can do a piece of work in 8 days while B alone can do it in 10...

    Text Solution

    |

  5. A can do a piece of work in 3 days while B can do the same work in 4 d...

    Text Solution

    |

  6. A alone can do a piece of work in 3 days, while B alone can do the sam...

    Text Solution

    |

  7. A can finish a work in 15 days, B in 20 days and C in 25 days. All the...

    Text Solution

    |

  8. A person can do a piece of work in 26 days and an another person can d...

    Text Solution

    |

  9. A alone can finish a work in 2 days, while B alone can finish it in 3 ...

    Text Solution

    |

  10. Vandana can do a piece of work in 10 days. With the help of Ruchi, she...

    Text Solution

    |

  11. A sum of money is sufficient to pay A's wages for 21 days and B's wage...

    Text Solution

    |

  12. Amit, Vipul and Kapil can do a piece of work in 12, 16 and 24 days, re...

    Text Solution

    |

  13. P, Q and R enter into a contract for a piece of work for Rs. 1100. P a...

    Text Solution

    |

  14. Ramesh and Suresh undertaken to do a piece of work for Rs. 800. Ramesh...

    Text Solution

    |

  15. A, B and C completed a work costing Rs 1800. A worked for 6 days, B wo...

    Text Solution

    |

  16. A and B undertaken to do a piece of work for Rs 1200. A alone can do i...

    Text Solution

    |

  17. A, B and C can do a piece of work in 20, 24 and 30 days, respectively....

    Text Solution

    |