A alone con finish a piece of work in 12...

A alone con finish a piece of work in 12 days and B alone can do it in 15 days. If both of them work at it together, how much time will they take to finish it ?

A

6 days

B

8 days

C

`6(2)/(3)` days

D

`10(1)/(5)` days

Text Solution

Verified by Experts

The correct Answer is:
C
Doubtnut Promotions Banner Mobile Dark
|

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 6 days and B alone can do it in 8 days. How long would it take for both of them to finish.

A alone can finish a piece of work in 10 days which B alone can finish in 15 days . If they work together and finish it , then out of total wages of Rs. 225 the amount in rupees that A will get .

Knowledge Check

  • A alone can finish a piece of work in 10 days which B alone can do in 15 days. If they work together and finish it, then out of total wages of Rs 3000, A will get

    A
    Rs 1200
    B
    Rs 1500
    C
    Rs 1800
    D
    Rs 20000
  • A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

    A
    9
    B
    8
    C
    10
    D
    6
  • A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish it, then out of a total wages of Rs. 75, A will get….

    A
    Rs. 30
    B
    Rs. 37.50
    C
    Rs. 45
    D
    Rs. 50
  • Similar Questions

    Explore conceptually related problems

    A can do a piece of work in 10 days while B alone can do it in 15 days . In how many days can both finish the same work?

    A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together?

    A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?

    A and B together can do a piece of work in 5 days and A alone can do it in 8 days. B alone can do the same piece of work in:

    A alone can do a piece of work in 6 days and B alone can do it in 8 days. A and B undertook to do it for Rs. 320 with the help of C, they finished it in 3 days. How much is paid to C ?