A, B and C three weavers have to supply ...

A, B and C three weavers have to supply an order of 100 shawls. A can weave a shawl in 2 hours, B in 3 hours and C in 4 hours respectively. It is known that even being a joint contract each one weaves his own shawl completely i.e no other weaver help to the rest weavers. In how many hours they will complete the order irrespective of day or night?

A

93 hours

B

100 hours

C

`92(4)/(13)` hours

D

94 hours

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 1)|100 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos
ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 2)
  1. A, B and C three weavers have to supply an order of 100 shawls. A can ...

    Text Solution

    |

  2. Arun and Satyam can complete a work individually in ,12 working days a...

    Text Solution

    |

  3. Kaushalya can do a work in 20 days, while Kaikeyi can do the same work...

    Text Solution

    |

  4. A and B can complete the work individually in 24 days and 30 days resp...

    Text Solution

    |

  5. In the previous question what per cent of the time of the morning shif...

    Text Solution

    |

  6. Working together B and C take 50% more number of days than A,B and C t...

    Text Solution

    |

  7. At Technosys Pvt Ltd. there are some engineering students employed as ...

    Text Solution

    |

  8. At Atharva Prakashan every book goes through 3 phases – typing, compos...

    Text Solution

    |

  9. If 12 men or 20 women can do a work in 54 days, then in how many days ...

    Text Solution

    |

  10. In the given pie-chart. what is the number of employees working in dep...

    Text Solution

    |

  11. Bunty and Babli working together completed a job in 8 days. If Bunty w...

    Text Solution

    |

  12. A single reservoir supplies the petrol to the whole city, while the re...

    Text Solution

    |

  13. In question 118, if m(1) and m(2) are the magnifications for two posit...

    Text Solution

    |

  14. A Contractor employed a certain number of workers to finish construct...

    Text Solution

    |

  15. Some-time after the new workers were introduced, all of the newly intr...

    Text Solution

    |

  16. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  17. Mr. stenley employed a certain number of typist for his project. 8 day...

    Text Solution

    |

  18. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  19. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |

  20. Mr. Stenley employed a tain number of typists for his project. 8 days ...

    Text Solution

    |