A can do a piece of work in 10 days, B c...

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A

9

B

8

C

10

D

6

Text Solution

Verified by Experts

The correct Answer is:
D
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

If A can do a piece of work in p days and B can do the same in q days: A and B together can finish it in how many days

A can do a piece of work in 4 days and B can do it in 12 days. In how many days will they finish the work, both working together ?

A can do a piece of work in 20 days and B in 15 days. With help of C, they finish the work in 5 days. C can alone do the work in

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

A and B together can do a piece of work in 10 days, B and C together can do it in 15 days while C and A together can do it in 20 days. Together they will complete the work in:

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. A can do a piece of work in 5 days, B can do it in 10 days. With the h...

    Text Solution

    |

  2. A can do a piece of work in 8 days, B can do it in 16 days, while C ca...

    Text Solution

    |

  3. A can do a piece of work in 10 days, B can do it in 15 days working to...

    Text Solution

    |

  4. A can do a piece of work in 24 days, while B can do it in 30 days. Wit...

    Text Solution

    |

  5. A can do a piece of work in 10 days. B can do it in 24 days. If C also...

    Text Solution

    |

  6. A can do a piece of work in 14 days while B can do it in 21 days. In h...

    Text Solution

    |

  7. A can do a piece of work in 24 days. If B is 60% more efficient than A...

    Text Solution

    |

  8. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  9. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  10. A is thrice as good a workman as B and takes 10 days less to do a piec...

    Text Solution

    |

  11. A is twice as good a workman as B and therefore A takes 6 days less th...

    Text Solution

    |

  12. A is thrice efficient as B and C is twice as efficient as B. What is t...

    Text Solution

    |

  13. Ajit is 3 times as efficient as Bablu, then the ratio of number of day...

    Text Solution

    |

  14. X is 4 times more efficient as Y, then the number of days taken by X a...

    Text Solution

    |

  15. If A takes 4//5 days as B takes and working together they require (20)...

    Text Solution

    |

  16. A is thrice as efficient as B. Working together they complete the work...

    Text Solution

    |

  17. A and B can do a piece of work in 8 days, B and C can do the same work...

    Text Solution

    |

  18. A and B can do a piece of work in 12 days, B and C in 15 days and C an...

    Text Solution

    |

  19. Ganga, Jamuna and Saraswati can do a piece of work. working together, ...

    Text Solution

    |

  20. A can finish a work in 12 days and B can do it in 15 days. After A had...

    Text Solution

    |