A is twice as good a workman as B and th...

A is twice as good a workman as B and therefore A takes 6 days less than B to finish the work individually. If A and B working complete together the work in 4 days, then how many days are required by B to complete the work alone?

A

12

B

18

C

8

D

6

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?

A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?

A is twice as good a workman as B and is therefore able to finish a piece of work in 30 days less than B. In how many days they can complete the whole work, working together?

A is 1.5 times efficient than B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed?

A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |

  2. A is thrice as good a workman as B and takes 10 days less to do a piec...

    Text Solution

    |

  3. A is twice as good a workman as B and therefore A takes 6 days less th...

    Text Solution

    |

  4. A is thrice efficient as B and C is twice as efficient as B. What is t...

    Text Solution

    |

  5. Ajit is 3 times as efficient as Bablu, then the ratio of number of day...

    Text Solution

    |

  6. X is 4 times more efficient as Y, then the number of days taken by X a...

    Text Solution

    |

  7. If A takes 4//5 days as B takes and working together they require (20)...

    Text Solution

    |

  8. A is thrice as efficient as B. Working together they complete the work...

    Text Solution

    |

  9. A and B can do a piece of work in 8 days, B and C can do the same work...

    Text Solution

    |

  10. A and B can do a piece of work in 12 days, B and C in 15 days and C an...

    Text Solution

    |

  11. Ganga, Jamuna and Saraswati can do a piece of work. working together, ...

    Text Solution

    |

  12. A can finish a work in 12 days and B can do it in 15 days. After A had...

    Text Solution

    |

  13. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  14. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  15. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  16. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to com...

    Text Solution

    |

  17. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  18. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  19. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  20. The ratio of efficiency of A is to C is 5:3. The ratio of number of da...

    Text Solution

    |