Home
Class 14
MATHS
A and B can complete a task in 30 days w...

A and B can complete a task in 30 days when working together after A and B have been working together for 11 days, B is called away and A, all by himself completes the task in the next 28 days. Had A been working alone, the number of days taken by him to complete the task would have been :

A

`33(3)/(19)`

B

`19(6)/2`

C

`44(4)/(19)`

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow the logic presented in the transcript and break it down into clear steps. ### Step 1: Determine the combined work rate of A and B A and B can complete a task together in 30 days. Therefore, their combined work rate is: \[ \text{Work rate of A + B} = \frac{1 \text{ task}}{30 \text{ days}} = \frac{1}{30} \text{ tasks per day} \] ### Step 2: Calculate the work done by A and B in 11 days In 11 days, the amount of work completed by A and B together is: \[ \text{Work done in 11 days} = 11 \times \frac{1}{30} = \frac{11}{30} \text{ tasks} \] ### Step 3: Determine the remaining work after 11 days The total work is 1 task. The remaining work after A and B have worked together for 11 days is: \[ \text{Remaining work} = 1 - \frac{11}{30} = \frac{30 - 11}{30} = \frac{19}{30} \text{ tasks} \] ### Step 4: Calculate the time taken by A to complete the remaining work After 11 days, B leaves, and A completes the remaining work in 28 days. Therefore, A's work rate can be calculated as: \[ \text{Work rate of A} = \frac{\text{Remaining work}}{\text{Time taken by A}} = \frac{\frac{19}{30}}{28} = \frac{19}{30 \times 28} = \frac{19}{840} \text{ tasks per day} \] ### Step 5: Calculate A's work rate in terms of total work Since we know A's work rate, we can express it in terms of the total work done: \[ \text{Total work done by A alone} = \text{Work rate of A} \times \text{Time taken by A alone} \] Let \( x \) be the number of days A would take to complete the entire task alone. Therefore: \[ \frac{1 \text{ task}}{x \text{ days}} = \frac{19}{840} \text{ tasks per day} \] This implies: \[ x = \frac{1}{\frac{19}{840}} = \frac{840}{19} \text{ days} \] ### Step 6: Calculate the value of \( x \) Now we compute \( \frac{840}{19} \): \[ 840 \div 19 = 44.21 \text{ days} \quad \text{(approximately)} \] ### Conclusion Thus, the number of days taken by A to complete the task alone is approximately: \[ \boxed{44 \frac{4}{19}} \text{ days} \]
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

If a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is

A alone can complete a task in 3 days. B alone can complete the same task in 7 days If A and B work together for 2 days, what fraction of the task will be left?

Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete the task working together?

A and B can complete a task in 30 days, whereas A,B and C can complete the same task in 21 days. In how many days can C alone complete the task?

A and B together can complete a work in 3 days. They start together but after 2 days, B left the work. If the work is completed after two more days, B alone could do the work in

A and B can complete a task in 30 days, whereas A. B and C can complete the same task in 21 days. In how many days can C alone complete the task?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. A can finish a work in 12 days and B can do it in 15 days. After A had...

    Text Solution

    |

  2. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  3. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  4. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  5. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to com...

    Text Solution

    |

  6. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  7. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  8. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  9. The ratio of efficiency of A is to C is 5:3. The ratio of number of da...

    Text Solution

    |

  10. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  11. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  12. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  13. In the previous question (number 33) if Zahira starts first then in ho...

    Text Solution

    |

  14. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  15. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  16. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  17. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |

  18. Alen and Border can do a work individually in 21 and 42 days respectiv...

    Text Solution

    |

  19. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  20. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |