Sonu can do a piece of work in 20 days. ...

Sonu can do a piece of work in 20 days. He started the work and left after some days, when `25%` work was done. After it Abhijeet joined and completed it working for 10 days. In how many days Sonu and Abhijeet can do the complete work, working together?

A

6

B

8

C

10

D

12

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?

A can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?

A can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?

A and B can do a piece of work in 20 days and 25 days. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A can do a piece of work in 12 days and B can do same work in 18 days. Both A and B start the work and after some days A left and B complete the remaining work in 8 days. After how many days will A left work?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  2. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  3. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  4. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to com...

    Text Solution

    |

  5. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  6. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  7. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  8. The ratio of efficiency of A is to C is 5:3. The ratio of number of da...

    Text Solution

    |

  9. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  10. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  11. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  12. In the previous question (number 33) if Zahira starts first then in ho...

    Text Solution

    |

  13. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  14. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  15. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  16. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |

  17. Alen and Border can do a work individually in 21 and 42 days respectiv...

    Text Solution

    |

  18. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  19. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |

  20. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |