Home
Class 14
MATHS
Kareena can do a piece of work in 9 days...

Kareena can do a piece of work in 9 days and Karishma can do the same work in 18 days. They started the work. After 3 days Shahid joined them, who can complete alone the same whole work in 3 days. What is the total number of days in which they had completed the work?

A

12

B

8

C

4

D

6

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the work efficiency of each person. - **Kareena's efficiency**: She can complete the work in 9 days. Therefore, her efficiency is: \[ \text{Efficiency of Kareena} = \frac{1 \text{ work}}{9 \text{ days}} = \frac{1}{9} \] - **Karishma's efficiency**: She can complete the work in 18 days. Therefore, her efficiency is: \[ \text{Efficiency of Karishma} = \frac{1 \text{ work}}{18 \text{ days}} = \frac{1}{18} \] - **Shahid's efficiency**: He can complete the work in 3 days. Therefore, his efficiency is: \[ \text{Efficiency of Shahid} = \frac{1 \text{ work}}{3 \text{ days}} = \frac{1}{3} \] ### Step 2: Calculate the total work done by Kareena and Karishma in the first 3 days. - Together, their combined efficiency for one day is: \[ \text{Combined efficiency} = \frac{1}{9} + \frac{1}{18} \] To add these fractions, we find a common denominator (which is 18): \[ \frac{1}{9} = \frac{2}{18} \] So, \[ \text{Combined efficiency} = \frac{2}{18} + \frac{1}{18} = \frac{3}{18} = \frac{1}{6} \] - In 3 days, the work done is: \[ \text{Work done in 3 days} = 3 \times \frac{1}{6} = \frac{3}{6} = \frac{1}{2} \] ### Step 3: Calculate the remaining work. - After 3 days, half of the work is completed. Therefore, the remaining work is: \[ \text{Remaining work} = 1 - \frac{1}{2} = \frac{1}{2} \] ### Step 4: Calculate the combined efficiency when Shahid joins. - Now, all three (Kareena, Karishma, and Shahid) are working together. Their combined efficiency is: \[ \text{Total efficiency} = \frac{1}{9} + \frac{1}{18} + \frac{1}{3} \] Again, finding a common denominator (which is 18): \[ \frac{1}{9} = \frac{2}{18}, \quad \frac{1}{3} = \frac{6}{18} \] So, \[ \text{Total efficiency} = \frac{2}{18} + \frac{1}{18} + \frac{6}{18} = \frac{9}{18} = \frac{1}{2} \] ### Step 5: Calculate the time taken to complete the remaining work. - The time taken to complete the remaining work of \(\frac{1}{2}\) at a rate of \(\frac{1}{2}\) work per day is: \[ \text{Time taken} = \frac{\text{Remaining work}}{\text{Total efficiency}} = \frac{\frac{1}{2}}{\frac{1}{2}} = 1 \text{ day} \] ### Step 6: Calculate the total time taken to complete the work. - The total time taken is the sum of the time worked by Kareena and Karishma alone and the time worked together with Shahid: \[ \text{Total time} = 3 \text{ days} + 1 \text{ day} = 4 \text{ days} \] ### Final Answer: The total number of days in which they completed the work is **4 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

Raja can do a piece of work in 14 days, while Rani can do the same work in 21 days. They started the work together but 3 days before the completion of the work, Raja left the work. The total number of days to complete the work is :

A can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?

A can do a piece of work in 4 days and B can complete the same work in 12 days. What is the number of days required to do the same work together?

A can do a piece of work in 4 days and B can complete the same work in 12 days . What is the number of days required to do the same work together ?

A can do a piece of work in 20 days and B can do same work in 25 days. Both A and B start the work and after 8 days A left. In how many days will the total work be completed ?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to com...

    Text Solution

    |

  2. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  3. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  4. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  5. The ratio of efficiency of A is to C is 5:3. The ratio of number of da...

    Text Solution

    |

  6. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  7. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  8. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  9. In the previous question (number 33) if Zahira starts first then in ho...

    Text Solution

    |

  10. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  11. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  12. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  13. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |

  14. Alen and Border can do a work individually in 21 and 42 days respectiv...

    Text Solution

    |

  15. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  16. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |

  17. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |

  18. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  19. 30 persons can do a piece of work in 24 days. How many more people are...

    Text Solution

    |

  20. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |