Home
Class 14
MATHS
The ratio of efficiency of A is to C is ...

The ratio of efficiency of A is to C is `5:3`. The ratio of number of days taken by B is to C is `2 : 3`. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :

A

4.5

B

5

C

6

D

`9(1)/(3)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the information provided and calculate the required values. ### Step 1: Understand the efficiency ratios - The efficiency ratio of A to C is given as \(5:3\). - This means if A's efficiency is \(5x\), then C's efficiency is \(3x\). ### Step 2: Determine the time ratios - The time taken by A and C will be the inverse of their efficiencies. Therefore, the time ratio of A to C is: \[ \text{Time ratio of A to C} = \frac{3}{5} \] - Let the time taken by C be \(5y\) days. Then, the time taken by A will be \(3y\) days. ### Step 3: Relate A's and C's time - It is given that A takes 6 days less than C: \[ 5y - 3y = 6 \implies 2y = 6 \implies y = 3 \] - Therefore, the time taken by C is: \[ 5y = 5 \times 3 = 15 \text{ days} \] - And the time taken by A is: \[ 3y = 3 \times 3 = 9 \text{ days} \] ### Step 4: Determine the efficiency of B - The ratio of the number of days taken by B to C is \(2:3\). Thus, if C takes \(15\) days, then B takes: \[ \text{Time taken by B} = \frac{2}{3} \times 15 = 10 \text{ days} \] - The efficiency of B will then be: \[ \text{Efficiency of B} = \frac{1}{10} \text{ of the work per day} \] - Since C takes 15 days, C's efficiency is: \[ \text{Efficiency of C} = \frac{1}{15} \text{ of the work per day} \] ### Step 5: Calculate total work - The total work can be calculated using A's efficiency: \[ \text{Total work} = \text{Efficiency of A} \times \text{Time taken by A} = 5 \times 9 = 45 \text{ units} \] ### Step 6: Work done by B and C in 2 days - B and C work together for 2 days: \[ \text{Work done in 2 days} = (B's \text{ efficiency} + C's \text{ efficiency}) \times 2 \] - B's efficiency is \( \frac{1}{10} \) and C's efficiency is \( \frac{1}{15} \): \[ \text{Work done in 2 days} = \left(\frac{1}{10} + \frac{1}{15}\right) \times 2 \] - To add these fractions, find a common denominator (30): \[ = \left(\frac{3}{30} + \frac{2}{30}\right) \times 2 = \left(\frac{5}{30}\right) \times 2 = \frac{1}{6} \times 2 = \frac{1}{3} \text{ of the total work} \] - Thus, the work done in 2 days is: \[ = \frac{1}{3} \times 45 = 15 \text{ units} \] ### Step 7: Remaining work - The remaining work after 2 days is: \[ \text{Remaining work} = 45 - 15 = 30 \text{ units} \] ### Step 8: Time taken by A to finish remaining work - A's efficiency is \(5\) units per day, so the time taken by A to finish the remaining work is: \[ \text{Time taken by A} = \frac{\text{Remaining work}}{\text{Efficiency of A}} = \frac{30}{5} = 6 \text{ days} \] ### Final Answer The number of days taken by A to finish the remaining work is **6 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :

The rates of working of A and B are in the ratio 3:4.The number of days taken by them to finish the work are in the ratio

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  2. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  3. The ratio of efficiency of A is to C is 5:3. The ratio of number of da...

    Text Solution

    |

  4. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  5. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  6. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  7. In the previous question (number 33) if Zahira starts first then in ho...

    Text Solution

    |

  8. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  9. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  10. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  11. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |

  12. Alen and Border can do a work individually in 21 and 42 days respectiv...

    Text Solution

    |

  13. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  14. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |

  15. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |

  16. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  17. 30 persons can do a piece of work in 24 days. How many more people are...

    Text Solution

    |

  18. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  19. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  20. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |