Home
Class 14
MATHS
The number of days required by A, B and ...

The number of days required by A, B and C to work individually is 6, 12 and 8 respectively. They started a work doing it alternatively. If A has started then followed by B and so on, how many days are needed to complete the whole work?

A

8

B

7.5

C

8.5

D

`9(1)/(2)`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to find out how many days A, B, and C will take to complete the work when they work alternatively. Let's break it down step by step. ### Step 1: Calculate the work efficiency of A, B, and C - A can complete the work in 6 days, so A's work efficiency is: \[ \text{Efficiency of A} = \frac{1}{6} \text{ (work per day)} \] - B can complete the work in 12 days, so B's work efficiency is: \[ \text{Efficiency of B} = \frac{1}{12} \text{ (work per day)} \] - C can complete the work in 8 days, so C's work efficiency is: \[ \text{Efficiency of C} = \frac{1}{8} \text{ (work per day)} \] ### Step 2: Calculate the total work done in 3 days Since they work alternatively, the work done in 3 days (A works on Day 1, B on Day 2, and C on Day 3) is: \[ \text{Total work in 3 days} = \text{Efficiency of A} + \text{Efficiency of B} + \text{Efficiency of C} \] Substituting the efficiencies: \[ = \frac{1}{6} + \frac{1}{12} + \frac{1}{8} \] ### Step 3: Find the least common multiple (LCM) to add the fractions The LCM of 6, 12, and 8 is 24. We convert each fraction: - For A: \[ \frac{1}{6} = \frac{4}{24} \] - For B: \[ \frac{1}{12} = \frac{2}{24} \] - For C: \[ \frac{1}{8} = \frac{3}{24} \] Now adding them together: \[ \text{Total work in 3 days} = \frac{4}{24} + \frac{2}{24} + \frac{3}{24} = \frac{9}{24} = \frac{3}{8} \] ### Step 4: Calculate how many sets of 3 days are needed to complete the work Since \( \frac{3}{8} \) of the work is done in 3 days, we can find out how many such sets are needed to complete 1 whole work: \[ \text{Number of sets required} = \frac{1}{\frac{3}{8}} = \frac{8}{3} \] ### Step 5: Calculate the total number of days Each set takes 3 days, so the total number of days required to complete the work is: \[ \text{Total days} = 3 \times \frac{8}{3} = 8 \text{ days} \] ### Final Answer Thus, the total number of days needed to complete the whole work is **8 days**. ---
Promotional Banner

Topper's Solved these Questions

  • TIME AND WORK

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|55 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • TIME AND WORK

    ARIHANT SSC|Exercise Final Round|15 Videos
  • THEORY OF EQUATIONS

    ARIHANT SSC|Exercise EXERCISE(LEVEL 2)|20 Videos
  • TIME, SPEED AND DISTANCE

    ARIHANT SSC|Exercise SPEED TEST (TSD)|10 Videos

Similar Questions

Explore conceptually related problems

A, B and C can do piece of work in 18,24 and 36 days respectively . They work alternately , first day C, second day B and third day A, fourth day C and so on. How many days will be needed to complete the work like this way?

Alen and Border can do a work individually in 21 and 42 days respectively. In how many days they can complete the work, working alternatively?

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A,B and C can do a piece of work in 12,18 and 9 days respectively. A started the work and worked for 4 days. Then B alone worked for 2 days. How many days would C alone take to complete the remaining work?

A,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?

A, B and C can do a piece of work individually in 8, 12 and 15 days respectively. A and B start working, but A quits after working for - 2 days. After this, C joins B till the completion of work. In how many days will the work be completed ?

ARIHANT SSC-TIME AND WORK-EXERCISE(LEVEL 1)
  1. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  2. In the previous question (number 33) if Zahira starts first then in ho...

    Text Solution

    |

  3. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  4. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  5. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  6. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |

  7. Alen and Border can do a work individually in 21 and 42 days respectiv...

    Text Solution

    |

  8. C takes twice the number of days to do a piece of work than A takes. A...

    Text Solution

    |

  9. When A, B and Care deployed for a task, A and B together do 70% of the...

    Text Solution

    |

  10. Colonel, Major and General started a work together for Rs. 816. Colone...

    Text Solution

    |

  11. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  12. 30 persons can do a piece of work in 24 days. How many more people are...

    Text Solution

    |

  13. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  14. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  15. 24 men can complete a job in 40 days. The number men required to compl...

    Text Solution

    |

  16. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  17. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  18. A certain job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  19. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  20. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |